News & Events

Verkler will celebrate it's 75th anniversary in 2010.

 

Posted by Jamie Hergott

Jeffersonville High School Project Overview

The overall project is 49% complete and we have expended approximately $18.5 million dollars. 

Units A/B - Addition
Installation of the metal roofing system at the main entrance and at the North and South entrances continues.  Ceiling grid and light fixtures have been erected in Unit A and we continue to work in Unit B.  The setting of casework is scheduled for November 11th.  Storefronts will be erected during the week of November 3rd thus allowing us to heat the new addition.  We are still scheduled to turnover this area to the Owner during Christmas Break, thus allowing construction trades to occupy the old administration area.

Units B and D, 2nd Floor
This area was completed and turned-over to the Owner for their use.  Sixteen classrooms will be transitioned from the middle section of the 2nd floor into the newly renovated classrooms.

Unit E – Main Entrance
A temporary enclosure has been erected in order to complete the interior finishes within the entrance.  Once the storefronts are complete at Units A/B addition, Unit E will be erected.

Unit F – Entrance and Cafeteria Expansion
The mechanical hook-ups to the new Air Handling Units are nearly complete.  In addition, the pulling of electrical wire and final terminations to the new switchgear will be completed this month.

Unit J – Gymnasium and Unit K Auxiliary Gymnasium
We have started erecting acoustical wall panels within the Auxiliary Gym and the completion of the panels will be performed over Christmas Break.

Unit J – Stairs and Elevator Addition
Concrete foundations will be complete by the middle of November.  Masonry contractor is scheduled to remobilize on November 10th to start erecting masonry at this location.  Elevator casing was drilled in early November.

  Schedule

Completion of Phase I   

December 2008

Completion of A/B Addition

December 2008
Transition of Data System Complete
Completion Date for Phase 2, 2nd Floor    Complete
Completion Date for Phase 3, 2nd Floor January 2009
Completion Date for Phase 3A, 2nd Floor April 2009
Commence Phase 4 Work April 2009
Commence Phase 5 Work June 2009
Completion of Project     August 1, 2010


Unit F Entrance and Cafeteria Addition


Erection of Interior Finishes at Unit F Entrance

 
Placement of Foundations at Stairway and Elevator Addition


2nd Floor Finishes


Erection of Ceilings and Lights at New Administration Area


Energizing of New Boilers

Click here for printable version.

Link
Link
Email this
Email
Close

7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS