Jeffersonville High School Project Overview

 
Exterior Skin of the Building 
-Along the North elevation, the upper half of the existing skin has been removed and replaced with drywall material.
-2 of 6 bays have been completed along the North elevation.  We will be starting our 3rd bay during the week of May 11th.

         

Unit A – Renovation of the Old Administration Area

Turnover to the Owner is scheduled for June 8th.

Unit A – New Science Classrooms

One of the science rooms has been turned-over to the Owner.

Unit B – New Addition, Science Rooms

Underground plumbing and electrical lines are complete for (3) science classrooms.

 

Units B and D, 2nd Floor, North Section of Building

-Ceiling grid is being erected.  Light fixtures are being placed within the ceiling grid system.  Interior walls are being painted.  Mechanical and electrical finishes are being installed.
-Scheduled to turnover the remaining classrooms June 8th.

Unit F – Loading Dock Area

Cooling towers and (1) of the chillers were activated during the week of May 4th.


Unit G – Industrial Art Classrooms (106, 107 & 108)

-The new air handling unit and new electrical switchgear have been placed in their designated locations at the elevated mechanical deck and hook-ups have commenced.


Unit J Existing Athletic Locker Rooms/Athletic Office (East of Gymnasium)

-The athletic office and trophy room have been renovated and turned-back over to the Owner.
-Working on the renovation of the Girl’s locker rooms.

Units J / K – Elevator / Corridor / Locker Room / Mechanical Addition

-The elevator contractor is nearly complete with the installation of the new elevator.
-Exterior finishes are being erected and finished.


Completion of Phase 1 Complete
Completion of A/B Addition Complete
Transition of Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor Complete
Commence Phase 4 Work June 2009
Commence Phase 5 Work Started
Completion Date for Phase 3A, 2nd Floor June 2009
Replace North & South Elevations on the 2nd Story Started
Renovation of the Media Center August 2009
Renovation of Kitchen/Cafeteria Areas August 2009
Replacement of the Main Stairs August 2009
Completion of the Project August 1, 2010



Re-skinning of the North Elevation


Renovation of the Remaining Classrooms on the 2nd Floor


Unit G, Mechanical Room


New Chiller

Click here for printable version of this report.

Link
Link
Email this
Email
Close

7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS