Jeffersonville High School Project Overview
Exterior Skin of the Building
-Along the North elevation, the upper half of the existing skin has been removed and replaced with drywall material.
-2 of 6 bays have been completed along the North elevation. We will be starting our 3rd bay during the week of May 11th.
Unit A – Renovation of the Old Administration Area
Turnover to the Owner is scheduled for June 8th.
Unit A – New Science Classrooms
One of the science rooms has been turned-over to the Owner.
Unit B – New Addition, Science Rooms
Underground plumbing and electrical lines are complete for (3) science classrooms.
Units B and D, 2nd Floor, North Section of Building
-Ceiling grid is being erected. Light fixtures are being placed within the ceiling grid system. Interior walls are being painted. Mechanical and electrical finishes are being installed.
-Scheduled to turnover the remaining classrooms June 8th.
Unit F – Loading Dock Area
Cooling towers and (1) of the chillers were activated during the week of May 4th.
Unit G – Industrial Art Classrooms (106, 107 & 108)
-The new air handling unit and new electrical switchgear have been placed in their designated locations at the elevated mechanical deck and hook-ups have commenced.
Unit J Existing Athletic Locker Rooms/Athletic Office (East of Gymnasium)
-The athletic office and trophy room have been renovated and turned-back over to the Owner.
-Working on the renovation of the Girl’s locker rooms.
Units J / K – Elevator / Corridor / Locker Room / Mechanical Addition
-The elevator contractor is nearly complete with the installation of the new elevator.
-Exterior finishes are being erected and finished.
| Completion of Phase 1 |
Complete |
| Completion of A/B Addition |
Complete |
| Transition of Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
Complete |
| Commence Phase 4 Work |
June 2009 |
| Commence Phase 5 Work |
Started |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Replace North & South Elevations on the 2nd Story |
Started |
| Renovation of the Media Center |
August 2009 |
| Renovation of Kitchen/Cafeteria Areas |
August 2009 |
| Replacement of the Main Stairs |
August 2009 |
| Completion of the Project |
August 1, 2010 |

Re-skinning of the North Elevation

Renovation of the Remaining Classrooms on the 2nd Floor

Unit G, Mechanical Room

New Chiller