News & Events

Verkler will celebrate it's 75th anniversary in 2010.

 

Posted by Jamie Hergott

Jeffersonville High School Project Overview

Units A/B - Addition 
Placement of foundations is nearly complete.  Majority of the structural steel is set with exception of the metal joists and decking.  Exterior masonry walls are being erected.  Mechanical and electrical underground continue to be placed within the building footprint in order to place the new concrete floors.

Unit J - Elevator/Stairs Addition
Topsoil has been removed, demolition has been completed and a temporary fence has been erected in order to isolate this area from students.  Placement of elevator foundations is being held-up due to an unforeseen storm line which is lying within our new building foundations.

Boiler Room
One of the existing chillers has been relocated and reconnected at its temporary location.  The old chiller and boilers have been removed from the building.  We are in the process of back-filling the recess area of the boiler room in order to pour a new concrete slab at the same elevation as the surrounding slabs.

The new boilers and pumps have been set and pipe connection to the mechanical units is complete. 

Unit A – Future Science Classrooms
As of June 4th, we started demolition activities within this classroom which will be followed by new foundations.

Unit C – Future Science Classrooms Renovation
Demolition activities and the placement of concrete are complete.  We are currently working on erecting structural steel within this classroom.    

Unit D - Classroom Renovation
Demolition activities, erection of structural steel, placement of concrete and erection of masonry walls are complete.  We are currently erecting new overhead installations within these classrooms.    

Unit E - Future MDF Room
Currently the Owner’s computer equipment has been relocated out of these rooms.  The demolition activities and the erection of interior walls are complete.  Painting is scheduled to start during the week of June 9th.   Once the flooring and painting are complete, the new MDF equipment will be set and terminated.

Unit E – Main Entrance
Started demolition activities at this building entrance and at the adjacent classroom. 

Units B and D, 2nd Floor
We have started the demolition activities for the 2nd floor classrooms.

Exterior Shell of the Building
We have started the removal of exterior facebrick and masonry block at the West elevation of the 2-story building followed immediately with the installation of new metal studs and drywall.

Roof Level
Existing chimney stack has been demolished to the roof level.  Roofing contractor continues to vacuum/remove all the loose rock from the various roof levels.  Application of the roofing system has commenced at the West elevation of the building and will proceed to the East elevation.

Site Work
The feeder conduit from the new electrical transformers to the new switchgear location has been installed.  The placement of the new transformer pads is complete and installation of the feeder conduit to Allison Lane is complete.  The new transformers that were furnished by Duke Energy have been set and will be energized once the electrical feeds have been installed from the interior switchgear to the new transformers.

 Greater Clark blog
Erection of exterior walls and structural steel at Units A/B

Greater Clark blog
Removal of main entrance tunnel

Greater Clark blog
Erection of new skin along west elevation

Greater Clark blog
Demolition of Unit E entrance

Greater Clark blog
Erection of masonry at Unit C science classroom

Greater Clark blog
Demolition of HVAC at gymnasium

 

Click here for printable version. 

Link
Link
Email this
Email
Close

7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS