News & Events

Verkler will celebrate it's 75th anniversary in 2010.

 

Posted by Jamie Hergott

Jeffersonville High School Project Overview

 

Areas that have been renovated and turned-back over to the Owner:

-Replacement of the Exterior Skin of the Building along the North & South elevations.
-Removal of the old ductwork system and replacement with new installations on the 1st floor corridors.
-Main stairs have been removed and the new stairs have been erected.  Majority of the finishes are complete with exception of the handrails.
-Old Administration Area has been converted into a new Clinic Area and Guidance Offices.
-Two existing science classrooms have been renovated.
- Units A and D, 2nd Floor, North and South Classrooms have been completed.
-Kitchen and Cafeteria Areas have been completely renovated.
-New Media Center is complete.
-Structural steel has been erected at the North and South entrances and final building finishes have been erected.
-Placement of the new Dumpster Area outside the Kitchen Area is complete.
-Painting of new installations within the Main and Auxiliary Gyms is complete.

Work continues at the following Areas:

-Renovation of 1st Floor, Science Classrooms and old Guidance Offices that were located along the South and West elevations of the 2-Story portion of the building.
-Renovation of 1st Floor classrooms that are located along the North and West elevations.
-Completion of (4) restrooms (1st & 2nd floors) next to the main stairs.
-Renovation of Boys PE Locker Rooms continues.
-Elevator and Stairs Addition continues.
-Unit K, Locker Room Addition continues.
-Unit G, Industrial Technology Area, pulling electrical wire from the switchgear to various electrical panels.

Schedule

Phase 1

Complete

A/B Addition

Complete

Transition of Data System

Complete

Phase 2, 2nd Floor

Complete

Phase 3, 2nd Floor

Complete

Phase 3A, 2nd Floor

Complete

Replace North & South Elevations of 2nd Story

Complete

Renovation of the Media Center

Complete

Renovation of the Kitchen & Cafeteria Areas

Complete

Commence Phase 4 Work

Started

Commence Phase 5 Work

Started

Replacement of the Main Stairs

Started

Completion of the Project

August 1, 2010

 

Click here for a printable version of this report.

Email thise-mail | permalinkpermalink
Posted by Jamie Hergott


Schedule
Phase 2, 1st Floor
New Restrooms at Main Stars Completed
Wrestling Locker Room December 2009
Phase 3, Unit G
Phase 1 December 2009
Phase 2 April 2010
Phase 3 July 2010
Phase 4, 1st Floor
North & West Classroom December 2009
Unit J, Elevator/Addition January 2010
Phase 5, 1st Floor
South Science Rooms (3 Total) December 2009
Softball Locker Room January 2010
Gym Vestibule and Adj. Restrooms January 2010
New Computer Rooms January 2010
West Science Room & Life Skills January 2010
3 Interior Science Rooms April 2010
Auditorium Restrooms July 2010
Unit E, Corridor Restrooms July 2010
Ceiling and Floor @ Corridors July 2010
Completion of the Project August 1, 2010

Click here for printable version of this report.

Email thise-mail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School
Project Overview

 

As of December, 2009, the overall project is 92% complete and we have expended approximately $35.1 million dollars.

Units A-D, 1st Floor Corridors 


In regards to the North side of the 2-story portion of the building, the new ceiling grid and light fixtures have been erected.  Twenty (20%) percent of the VCT tile has been laid.

 

Also, the erection of ceilings on the Southern portion of the building has commenced.  Currently the contractor has started at Unit D and is proceeding eastward.

 

Unit B Science Classrooms

Demolition of the interior classrooms has begun.


Unit D Science Room, Moderate Classrooms and Life Skills Lab

 

The perimeter classrooms along the Southern and Western elevations of the 2-story portion of the building have been turned-over to the Owner and are being occupied by teachers and students.

 

Unit D Renovation of Old Bookstore Area

The interior walls have been erected.  Walls and overhead rough-ins are complete. 

 

Unit D Computer Rooms

Renovation of both rooms is complete and a pre-punch inspection is being performed prior to the rooms being turned-over to the Owner.


Unit E Toilet Rooms
The renovation of girl’s toilet room is on hold until we receive a new exhaust fan for the area.  This is an unforeseen design change.

 

Unit F Elevator

In the process of completing additional requests prior to requesting the State elevator inspection.


Unit G Rooms G106 thru G108

Erection of ceiling grid and light fixtures are complete.  Placement of ceiling tiles will be performed after the overhead inspection.  Placement of flooring and the installation of millwork are scheduled for Monday, March 15th.


Unit J Football Lockers

Demolition is scheduled to start today in this area.

 

Unit J North Toilet Rooms
Pre-punching of the rooms is scheduled to be complete by Thursday of this week in order to facilitate the turn-over to the Owner.


Click here for a printable version of this report.

Email thise-mail | permalinkpermalink

7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS