Jeffersonville High School
Project Overview
Exterior Skin of the Building (North & South Elevations)Demolition and erection of exterior metal studs & sheathing are complete. We are continuing to erect masonry, EIFS and windows.
Corridors (1st Floor) -Old ductwork has been removed from the main corridor and is being replaced with new ductwork. -he main stairs have been removed and the new structural stairs are being erected. Placement of terrazzo will commence after erection.
Unit A - Renovation of the Old Administration Area This area is complete and ready for inspection in regards to generating a punch list.
Unit B - New Science Classrooms -wo science rooms are being renovated and waiting for casework delivery in order to commence VCT installation. -ainting of walls and the erection of ceilings are complete.
Units A and C, 2nd Floor, North Section of Building The East and West classrooms have been turned-over to the Owner for move-in. Carpet is being laid in these rooms. Casework is located on-site.
Unit F - Kitchen Area All underground installations are complete. The concrete slab has been replaced. The erection of masonry walls is complete. The freezer/cooler curbs have been set. All overhead installations will be complete by July 22nd.
Unit F Cafeteria Area ll overhead installations are complete. All masonry work is complete.
Unit G - Industrial Art Classrooms (Rooms 106, 107 & 108) Continue to pull electrical wire from the new electrical switchgear to their designated electrical panels.
Unit J Main / Auxiliary Gymnasiums The installations that were installed last summer are being painted this summer.
Unit J Existing Athletic Locker Rooms/Athletic Office (East Side of Gymnasium) We started renovating the Boy's locker room which is the last phase along the East side of the gym.
Schedule
| Completion of Phase 1 |
Complete |
| Completion of A/B Addition |
Complete |
| Transition of Data System |
Complete |
| Completion of Data for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
Complete
|
| Commence Phase 4 Work |
June 2009 |
| Commence Phase 5 Work |
Started |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Replace North & South Elevations of the 2nd Story |
Started |
| Renovation of the Media Center |
August 2009 |
| Renovation of the Kitchen & Cafeteria Areas |
August 2009 |
| Replacement of the Main Stairs |
August 2009 |
| Completion of the Project |
August 1, 2010 |
|
|
New Clinic Area
 Renovation of 2nd Floor Classrooms
Renovated Restrooms on 2nd Floor
Unit J Addition
Installation of Ceilings Within Cafeteria
Erection of Bulkhead within Media CenterFor a printable version of this report, click here.
|
|
|