Project Overview

 Exterior Skin of the Building (North & South Elevations)Demolition and erection of exterior metal studs & sheathing are complete. We are continuing to erect masonry, EIFS and windows.

Corridors (1st Floor)
-Old ductwork has been removed from the main corridor and is being replaced with new ductwork.
-he main stairs have been removed and the new structural stairs are being erected. Placement of terrazzo will commence after erection.

Unit A - Renovation of the Old Administration Area This area is complete and ready for inspection in regards to generating a punch list.

Unit B - New Science Classrooms
-wo science rooms are being renovated and waiting for casework delivery in order to commence VCT installation.
-ainting of walls and the erection of ceilings are complete.

Units A and C, 2nd Floor, North Section of Building
The East and West classrooms have been turned-over to the Owner for move-in. Carpet is being laid in these rooms. Casework is located on-site.

Unit F - Kitchen Area
All underground installations are complete. The concrete slab has been replaced. The erection of masonry walls is complete. The freezer/cooler curbs have been set. All overhead installations will be complete by July 22nd.

Unit F Cafeteria Area
ll overhead installations are complete. All masonry work is complete.

Unit G - Industrial Art Classrooms (Rooms 106, 107 & 108)
Continue to pull electrical wire from the new electrical switchgear to their designated electrical panels.

Unit J Main / Auxiliary Gymnasiums
The installations that were installed last summer are being painted this summer.

Unit J Existing Athletic Locker Rooms/Athletic Office (East Side of Gymnasium)
We started renovating the Boy's locker room which is the last phase along the East side of the gym.

Schedule

Completion of Phase 1 Complete
Completion of A/B Addition Complete
Transition of Data System Complete
Completion of Data for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor Complete
Commence Phase 4 Work June 2009
Commence Phase 5 Work Started
Completion Date for Phase 3A, 2nd Floor June 2009
Replace North & South Elevations of the 2nd Story Started
Renovation of the Media Center August 2009
Renovation of the Kitchen & Cafeteria Areas August 2009
Replacement of the Main Stairs August 2009
Completion of the Project August 1, 2010


New Clinic Area


Renovation of 2nd Floor Classrooms


Renovated Restrooms on 2nd Floor


Unit J Addition


Installation of Ceilings Within Cafeteria


Erection of Bulkhead within Media Center

For a printable version of this report, click here.
Email thise-mail | permalinkpermalink

7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS