Jeffersonville High School Project Overview
Exterior Skin of the Building
-Along the North elevation, the upper half of the existing skin has been removed and replaced with drywall material.
-2 of 6 bays have been completed along the North elevation. We will be starting our 3rd bay during the week of May 11th.
Unit A – Renovation of the Old Administration Area
Turnover to the Owner is scheduled for June 8th.
Unit A – New Science Classrooms
One of the science rooms has been turned-over to the Owner.
Unit B – New Addition, Science Rooms
Underground plumbing and electrical lines are complete for (3) science classrooms.
Units B and D, 2nd Floor, North Section of Building
-Ceiling grid is being erected. Light fixtures are being placed within the ceiling grid system. Interior walls are being painted. Mechanical and electrical finishes are being installed.
-Scheduled to turnover the remaining classrooms June 8th.
Unit F – Loading Dock Area
Cooling towers and (1) of the chillers were activated during the week of May 4th.
Unit G – Industrial Art Classrooms (106, 107 & 108)
-The new air handling unit and new electrical switchgear have been placed in their designated locations at the elevated mechanical deck and hook-ups have commenced.
Unit J Existing Athletic Locker Rooms/Athletic Office (East of Gymnasium)
-The athletic office and trophy room have been renovated and turned-back over to the Owner.
-Working on the renovation of the Girl’s locker rooms.
Units J / K – Elevator / Corridor / Locker Room / Mechanical Addition
-The elevator contractor is nearly complete with the installation of the new elevator.
-Exterior finishes are being erected and finished.
| Completion of Phase 1 |
Complete |
| Completion of A/B Addition |
Complete |
| Transition of Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
Complete |
| Commence Phase 4 Work |
June 2009 |
| Commence Phase 5 Work |
Started |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Replace North & South Elevations on the 2nd Story |
Started |
| Renovation of the Media Center |
August 2009 |
| Renovation of Kitchen/Cafeteria Areas |
August 2009 |
| Replacement of the Main Stairs |
August 2009 |
| Completion of the Project |
August 1, 2010 |

Re-skinning of the North Elevation

Renovation of the Remaining Classrooms on the 2nd Floor

Unit G, Mechanical Room

New Chiller
Click here for printable version of this report.
Jeffersonville High School Project Overview
The overall project is 64% complete.
Unit A - Old Administration Area and Unit A - Science Classrooms
Continue to erect interior walls and install mechanical, electrical and plumbing rough-ins.
New masonry walls are complete.
Unit B – New Addition, Science Rooms
Demolition is complete and installation of underground plumbing lines has started.
Units B and D, 2nd Floor, North Section of Building
Demolition is complete and we have started installing mechanical and electrical overhead installations.
Unit F – Loading Dock Area
Cooling towers and (1) of the chillers are scheduled to be activated by May 1st.
Unit G – Industrial Art Classrooms (106, 107 & 108)
The elevated mechanical deck has been erected and the slab-on-deck has been placed. All mechanical / electrical equipment that rest on this deck are located on-site.
Units J / K – Locker Room / Mechanical Addition
A portion of the roofing system was placed during Spring Break.
The elevator contractor has mobilized and has started installation of the new elevator.
All new concrete slabs have been placed with the exception of the entrance to the Athletic Director’s office.
Schedule
| Completion of Phase 1 |
Complete |
| Completion of A/B Addition |
Complete |
| Transition of Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
Complete |
| Commence Phase 4 Work |
June 2009 |
| Commence Phase 5 Work |
Started |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Replace North & South Elevations of the 2-Story |
August 2009 |
| Renovation of the Media Center |
August 2009 |
| Renovation of Kitchen & Cafeteria Areas |
August 2009 |
| Replacement of the Main Stars |
August 2009 |
| Completion of the Project |
August 1, 2010 |

Enclosure of Units F and J

Erection of new building skin along south elevation.
Erection of new walls at new administration area.
Interior Finishes at 2nd floor, middle corridor
Click here for printable version.
Jeffersonville High School Project Overview
The overall project is 61% complete.
Unit A - Old Administration Area and Science Classroom
During the 1st week of March we started demolition work within the old administration area. In addition, we recommenced our work within Unit A science classroom.
Unit B – New Addition, Science Rooms
Science classrooms have been turned-over to the Owner for occupancy.
Units B and D, 2nd Floor, Middle Section of Building
The next set of (16) classrooms are scheduled to be turned-over March 13th.
Unit F – Loading Dock Area
The new emergency generator was energized this past month. Continuing to route chilled water lines to the cooling towers and chillers.
Unit G – Industrial Art Classrooms (106, 107 & 108)
Demolition and placement of foundations within these classrooms is complete and we are ready for steel erection.
Units J / K – Locker Room / Mechanical Addition
Continuing to erect exterior masonry walls. Placement of floor slabs and setting of mechanical equipment are scheduled to be complete this month.
Schedule
| Completion of Phase I |
Complete |
| Completion of A/B Addition |
Complete |
| Transition of Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Replace North & South Elevations of the 2-Story |
August 2009 |
| Renovation of the Media Center |
August 2009 |
| Renovation of the Kitchen & Cafeteria Areas |
August 2009 |
| Replacement of the Main Stairs |
August 2009 |
| Completion Date for Phase 3, 2nd Floor |
March 2009 |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Commence Phase 4 Work |
April 2009 |
| Commence Phase 5 Work |
June 2009 |
| Completion of Project |
August 1, 2010 |
New Science Rooms
New Science Rooms

Renovation of 2nd Set of Classrooms
New Locker Rooms/Mechanical Mezzanine Addition
Click here for a printable version of this report.
Jeffersonville High School Project Overview
The overall project is 60% complete and we have expended approximately $22 million dollars.
Unit B - New Addition, Science Rooms
Casework has been installed. Mechanical and electrical hook-ups at each work station are complete.
Units B and D, 2nd Floor, Middle Section of Building
Interior finishes are proceeding and the turnover date for this phase is early March.
Unit F - Loading Dock Area
New Cooling Towers and Emergency Generator have been set in their permanent location outside the Boiler Room. We are proceeding on infilling existing louver openings and the setting of new louvers.
Unit F - Entrance and Cafeteria Expansion
Placement of exterior Patio Area and sidewalks/steps are complete.
Units J / K - Locker Room / Mechanical Addition
Structural Steel has been erected and detailed. Continuing to erect exterior masonry walls (weather dependant).
Schedule
| Completion of Phase I |
Complete |
| Completion of A/B Addition |
Complete |
| Transition Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
March 2009 |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Commence Phase 4 Work |
April 2009 |
| Commence Phase 5 Work |
June 2009 |
| Completion of the Project |
August 1, 2010 |
Setting of New Cooling Towers & Generator

Erection of Structural Steel @ Vestibule / Mechanical Room Addition

Placement of Cafeteria Patio and Steps

New Addition - Science Room

Renovation of 2nd Floor Classroom
Click here for printable version.
Jeffersonville High School Project Overview
The overall project is 53% complete and we have expended approximately $20.2 million dollars.
Units A/B - Addition
-Interior Finishes
-Owner Move-In
Units B and D, 2nd Floor, Middle Section of Building
-Demolition Work
Unit E - Main/North Entrance
-Storefronts
-Ceiling Grid Followed by Light Fixtures & Ceiling Pads
-Flooring
Unit F - Entrance and Cafeteria Expansion
-Building Enclosure
-Overhead Rough-Ins
Unit J - Gymnasium and Unit K Auxiliary Gymnasium
-Auxiliary Gym - Acoustical Wall & Ceiling Panels
-Air Handling Units
Unit J - Stairs and Elevator Addition
-Elevator Shaft
-Erecting Masonry Exterior Walls
Schedule
| Completion of Phase 1 |
December 2008 |
| Completion of A/B Addition |
December 2008 |
| Transition of Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
March 2009 |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Commence Phase 4 Work |
April 2009 |
| Commence Phase 5 Work |
June 2009 |
| Completion of the Project |
August 1, 2010 |

New Administration Area

Construction of New Science Lab

Construction of New Elevator/Stairs Addition

Construction of New South Entrance

New Entrance at Bus Drop-Off

Newly Renovated 2nd Floor Corridors