News & Events

Verkler will celebrate it's 75th anniversary in 2010.

 

Posted by Jamie Hergott

Jeffersonville High School

Project Overview

 Exterior Skin of the Building (North & South Elevations)Demolition and erection of exterior metal studs & sheathing are complete. We are continuing to erect masonry, EIFS and windows.

Corridors (1st Floor)
-Old ductwork has been removed from the main corridor and is being replaced with new ductwork.
-he main stairs have been removed and the new structural stairs are being erected. Placement of terrazzo will commence after erection.

Unit A - Renovation of the Old Administration Area This area is complete and ready for inspection in regards to generating a punch list.

Unit B - New Science Classrooms
-wo science rooms are being renovated and waiting for casework delivery in order to commence VCT installation.
-ainting of walls and the erection of ceilings are complete.

Units A and C, 2nd Floor, North Section of Building
The East and West classrooms have been turned-over to the Owner for move-in. Carpet is being laid in these rooms. Casework is located on-site.

Unit F - Kitchen Area
All underground installations are complete. The concrete slab has been replaced. The erection of masonry walls is complete. The freezer/cooler curbs have been set. All overhead installations will be complete by July 22nd.

Unit F Cafeteria Area
ll overhead installations are complete. All masonry work is complete.

Unit G - Industrial Art Classrooms (Rooms 106, 107 & 108)
Continue to pull electrical wire from the new electrical switchgear to their designated electrical panels.

Unit J Main / Auxiliary Gymnasiums
The installations that were installed last summer are being painted this summer.

Unit J Existing Athletic Locker Rooms/Athletic Office (East Side of Gymnasium)
We started renovating the Boy's locker room which is the last phase along the East side of the gym.

Schedule

Completion of Phase 1 Complete
Completion of A/B Addition Complete
Transition of Data System Complete
Completion of Data for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor Complete
Commence Phase 4 Work June 2009
Commence Phase 5 Work Started
Completion Date for Phase 3A, 2nd Floor June 2009
Replace North & South Elevations of the 2nd Story Started
Renovation of the Media Center August 2009
Renovation of the Kitchen & Cafeteria Areas August 2009
Replacement of the Main Stairs August 2009
Completion of the Project August 1, 2010


New Clinic Area


Renovation of 2nd Floor Classrooms


Renovated Restrooms on 2nd Floor


Unit J Addition


Installation of Ceilings Within Cafeteria


Erection of Bulkhead within Media Center

For a printable version of this report, click here.
Email thise-mail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

 
Exterior Skin of the Building 
-Along the North elevation, the upper half of the existing skin has been removed and replaced with drywall material.
-2 of 6 bays have been completed along the North elevation.  We will be starting our 3rd bay during the week of May 11th.

         

Unit A – Renovation of the Old Administration Area

Turnover to the Owner is scheduled for June 8th.

Unit A – New Science Classrooms

One of the science rooms has been turned-over to the Owner.

Unit B – New Addition, Science Rooms

Underground plumbing and electrical lines are complete for (3) science classrooms.

 

Units B and D, 2nd Floor, North Section of Building

-Ceiling grid is being erected.  Light fixtures are being placed within the ceiling grid system.  Interior walls are being painted.  Mechanical and electrical finishes are being installed.
-Scheduled to turnover the remaining classrooms June 8th.

Unit F – Loading Dock Area

Cooling towers and (1) of the chillers were activated during the week of May 4th.


Unit G – Industrial Art Classrooms (106, 107 & 108)

-The new air handling unit and new electrical switchgear have been placed in their designated locations at the elevated mechanical deck and hook-ups have commenced.


Unit J Existing Athletic Locker Rooms/Athletic Office (East of Gymnasium)

-The athletic office and trophy room have been renovated and turned-back over to the Owner.
-Working on the renovation of the Girl’s locker rooms.

Units J / K – Elevator / Corridor / Locker Room / Mechanical Addition

-The elevator contractor is nearly complete with the installation of the new elevator.
-Exterior finishes are being erected and finished.


Completion of Phase 1 Complete
Completion of A/B Addition Complete
Transition of Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor Complete
Commence Phase 4 Work June 2009
Commence Phase 5 Work Started
Completion Date for Phase 3A, 2nd Floor June 2009
Replace North & South Elevations on the 2nd Story Started
Renovation of the Media Center August 2009
Renovation of Kitchen/Cafeteria Areas August 2009
Replacement of the Main Stairs August 2009
Completion of the Project August 1, 2010



Re-skinning of the North Elevation


Renovation of the Remaining Classrooms on the 2nd Floor


Unit G, Mechanical Room


New Chiller

Click here for printable version of this report.

Email thise-mail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

 
The overall project is 64% complete.

 
Unit A - Old Administration Area and Unit A - Science Classrooms

Continue to erect interior walls and install mechanical, electrical and plumbing rough-ins.
New masonry walls are complete.

Unit B – New Addition, Science Rooms

Demolition is complete and installation of underground plumbing lines has started.
 

Units B and D, 2nd Floor, North Section of Building

Demolition is complete and we have started installing mechanical and electrical overhead installations.


Unit F – Loading Dock Area

Cooling towers and (1) of the chillers are scheduled to be activated by May 1st.

Unit G – Industrial Art Classrooms (106, 107 & 108)
The elevated mechanical deck has been erected and the slab-on-deck has been placed.  All mechanical / electrical equipment that rest on this deck are located on-site.   

 
Units J / K – Locker Room / Mechanical Addition

A portion of the roofing system was placed during Spring Break.
The elevator contractor has mobilized and has started installation of the new elevator.
All new concrete slabs have been placed with the exception of the entrance to the Athletic Director’s office.

Schedule

Completion of Phase 1 Complete
Completion of A/B Addition Complete
Transition of Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor Complete
Commence Phase 4 Work June 2009
Commence Phase 5 Work Started
Completion Date for Phase 3A, 2nd Floor June 2009
Replace North & South Elevations of the 2-Story August 2009
Renovation of the Media Center August 2009
Renovation of Kitchen & Cafeteria Areas August 2009
Replacement of the Main Stars August 2009
Completion of the Project August 1, 2010

 

Enclosure of Units F and J

Erection of new building skin along south elevation.


Erection of new walls at new administration area.


Interior Finishes at 2nd floor, middle corridor

Click here for printable version.
Email thise-mail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview


The overall project is 61% complete.


Unit A - Old Administration Area and Science Classroom
During the 1st week of March we started demolition work within the old administration area. In addition, we recommenced our work within Unit A science classroom.

 

Unit B – New Addition, Science Rooms

Science classrooms have been turned-over to the Owner for occupancy.

Units B and D, 2nd Floor, Middle Section of Building

The next set of (16) classrooms are scheduled to be turned-over March 13th.

 
Unit F – Loading Dock Area

The new emergency generator was energized this past month. Continuing to route chilled water lines to the cooling towers and chillers.


Unit G – Industrial Art Classrooms (106, 107 & 108)

Demolition and placement of foundations within these classrooms is complete and we are ready for steel erection.

 

Units J / K – Locker Room / Mechanical Addition

Continuing to erect exterior masonry walls.  Placement of floor slabs and setting of mechanical equipment are scheduled to be complete this month.

  Schedule

Completion of Phase I Complete
Completion of A/B Addition Complete
Transition of Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Replace North & South Elevations  of the 2-Story August 2009
Renovation of the Media Center August 2009
Renovation of the Kitchen & Cafeteria Areas August 2009
Replacement of the Main Stairs August 2009
Completion Date for Phase 3, 2nd Floor March 2009
Completion Date for Phase 3A, 2nd Floor June 2009
Commence Phase 4 Work April 2009
Commence Phase 5 Work June 2009
Completion of Project August 1, 2010


New Science Rooms


New Science Rooms

Renovation of 2nd Set of Classrooms


New Locker Rooms/Mechanical Mezzanine Addition

Click here for a printable version of this report.
Email thise-mail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

The overall project is 60% complete and we have expended approximately $22 million dollars.

Unit B - New Addition, Science Rooms
Casework has been installed. Mechanical and electrical hook-ups at each work station are complete.

Units B and D, 2nd Floor, Middle Section of Building
 Interior finishes are proceeding and the turnover date for this phase is early March.

Unit F - Loading Dock Area
New Cooling Towers and Emergency Generator have been set in their permanent location outside the Boiler Room. We are proceeding on infilling existing louver openings and the setting of new louvers.

Unit F - Entrance and Cafeteria Expansion
Placement of exterior Patio Area and sidewalks/steps are complete.

Units J / K - Locker Room / Mechanical Addition
Structural Steel has been erected and detailed. Continuing to erect exterior masonry walls (weather dependant).

Schedule

Completion of Phase I Complete
Completion of A/B Addition Complete
Transition Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor March 2009
Completion Date for Phase 3A, 2nd Floor June 2009
Commence Phase 4 Work April 2009
Commence Phase 5 Work June 2009
Completion of the Project August 1, 2010
















Setting of New Cooling Towers & Generator


Erection of Structural Steel @ Vestibule / Mechanical Room Addition


Placement of Cafeteria Patio and Steps


New Addition - Science Room


Renovation of 2nd Floor Classroom

Click here for printable version.

Email thise-mail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

The overall project is 58% complete and we have expended approximately $22 million dollars. 

Unit A – New Addition, Administration Area
    -Interior Finishes will be complete this week
    -Sprinkler System will be activated on January 14th

Unit B – New Addition, Science Rooms
    -Casework will be installed during the week of January 12th.
    -Mechanical and electrical installations will follow.

Units B and D, 2nd Floor, Middle Section of Building
    -Overhead Rough-Ins are proceeding
    -Drywall bulkheads are being erected
    -Painting has commenced

 Unit E – Main/North Entrance
    -Flooring was completed over Christmas Break

Unit F – Entrance and Cafeteria Expansion
    -Complete the Building Enclosure
    -Work on the Patio Area and future Sidewalks/Steps

Unit J – Gymnasium and Unit K Auxiliary Gymnasium
    -Auxiliary Gym - Acoustical Wall & Ceiling Panels
    -Roof-Top Exhaust Fans are operational
    -New Mechanical Units were placed in the old weight lifting room.

Unit J – Stairs and Elevator Addition
    -Erecting Masonry Exterior Walls

Units J/K – Locker Room / Mechanical Addition
    -Building foundations have been placed

Schedule

Completion of Phase 1     Complete    
Completion of A/B Addition     Complete
Transition of Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor March 2009
Completion Date for Phase 3A, 2nd Floor June 2009
Commence Phase 4 Work April 2009
Commence Phase 5 Work June 2009
Completion of the Project August 1, 2010

Greater Clark County Schools
New Entrance at Bus Parking Lot

Greater Clark County Schools
Erection of Acoustical Panels at Auxiliary Gym

Greater Clark County Schools
Area Outside Cafeteria

Greater Clark County Schools
Setting of New Chillers

Click here for printable version.

Email thise-mail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

The overall project is 53% complete and we have expended approximately $20.2 million dollars.

Units A/B - Addition
    -Interior Finishes
    -Owner Move-In

Units B and D, 2nd Floor, Middle Section of Building
    -Demolition Work

Unit E - Main/North Entrance
    -Storefronts
    -Ceiling Grid Followed by Light Fixtures & Ceiling Pads
    -Flooring

Unit F - Entrance and Cafeteria Expansion
    -Building Enclosure
    -Overhead Rough-Ins

Unit J - Gymnasium and Unit K Auxiliary Gymnasium
    -Auxiliary Gym - Acoustical Wall & Ceiling Panels
    -Air Handling Units

Unit J - Stairs and Elevator Addition
    -Elevator Shaft
    -Erecting Masonry Exterior Walls

 Schedule

Completion of Phase 1     December 2008
Completion of A/B Addition                        December 2008
Transition of Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor March 2009
Completion Date for Phase 3A, 2nd Floor June 2009
Commence Phase 4 Work April 2009
Commence Phase 5 Work June 2009
Completion of the Project August 1, 2010

 

Greater Clark County Schools
New Administration Area

 

Greater Clark County Schools
Construction of New Science Lab

 

Greater Clark County Schools
Construction of New Elevator/Stairs Addition

 

Greater Clark County Schools
Construction of New South Entrance

 

Greater Clark County Schools
New Entrance at Bus Drop-Off

 

Greater Clark County Schools
Newly Renovated 2nd Floor Corridors

Click here for printable version.

Email thise-mail | permalinkpermalink

7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS