News & Events

Verkler will celebrate it's 75th anniversary in 2010.

 

Posted by Jamie Hergott

Jeffersonville High School Project Overview

 

Areas that have been renovated and turned-back over to the Owner:

-Replacement of the Exterior Skin of the Building along the North & South elevations.
-Removal of the old ductwork system and replacement with new installations on the 1st floor corridors.
-Main stairs have been removed and the new stairs have been erected.  Majority of the finishes are complete with exception of the handrails.
-Old Administration Area has been converted into a new Clinic Area and Guidance Offices.
-Two existing science classrooms have been renovated.
- Units A and D, 2nd Floor, North and South Classrooms have been completed.
-Kitchen and Cafeteria Areas have been completely renovated.
-New Media Center is complete.
-Structural steel has been erected at the North and South entrances and final building finishes have been erected.
-Placement of the new Dumpster Area outside the Kitchen Area is complete.
-Painting of new installations within the Main and Auxiliary Gyms is complete.

Work continues at the following Areas:

-Renovation of 1st Floor, Science Classrooms and old Guidance Offices that were located along the South and West elevations of the 2-Story portion of the building.
-Renovation of 1st Floor classrooms that are located along the North and West elevations.
-Completion of (4) restrooms (1st & 2nd floors) next to the main stairs.
-Renovation of Boys PE Locker Rooms continues.
-Elevator and Stairs Addition continues.
-Unit K, Locker Room Addition continues.
-Unit G, Industrial Technology Area, pulling electrical wire from the switchgear to various electrical panels.

Schedule

Phase 1

Complete

A/B Addition

Complete

Transition of Data System

Complete

Phase 2, 2nd Floor

Complete

Phase 3, 2nd Floor

Complete

Phase 3A, 2nd Floor

Complete

Replace North & South Elevations of 2nd Story

Complete

Renovation of the Media Center

Complete

Renovation of the Kitchen & Cafeteria Areas

Complete

Commence Phase 4 Work

Started

Commence Phase 5 Work

Started

Replacement of the Main Stairs

Started

Completion of the Project

August 1, 2010

 

Click here for a printable version of this report.

Email thisemail | permalinkpermalink
Posted by Jamie Hergott


Schedule
Phase 2, 1st Floor
New Restrooms at Main Stars Completed
Wrestling Locker Room December 2009
Phase 3, Unit G
Phase 1 December 2009
Phase 2 April 2010
Phase 3 July 2010
Phase 4, 1st Floor
North & West Classroom December 2009
Unit J, Elevator/Addition January 2010
Phase 5, 1st Floor
South Science Rooms (3 Total) December 2009
Softball Locker Room January 2010
Gym Vestibule and Adj. Restrooms January 2010
New Computer Rooms January 2010
West Science Room & Life Skills January 2010
3 Interior Science Rooms April 2010
Auditorium Restrooms July 2010
Unit E, Corridor Restrooms July 2010
Ceiling and Floor @ Corridors July 2010
Completion of the Project August 1, 2010

Click here for printable version of this report.

Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School
Project Overview

 

As of December, 2009, the overall project is 92% complete and we have expended approximately $35.1 million dollars.

Units A-D, 1st Floor Corridors 


In regards to the North side of the 2-story portion of the building, the new ceiling grid and light fixtures have been erected.  Twenty (20%) percent of the VCT tile has been laid.

 

Also, the erection of ceilings on the Southern portion of the building has commenced.  Currently the contractor has started at Unit D and is proceeding eastward.

 

Unit B Science Classrooms

Demolition of the interior classrooms has begun.


Unit D Science Room, Moderate Classrooms and Life Skills Lab

 

The perimeter classrooms along the Southern and Western elevations of the 2-story portion of the building have been turned-over to the Owner and are being occupied by teachers and students.

 

Unit D Renovation of Old Bookstore Area

The interior walls have been erected.  Walls and overhead rough-ins are complete. 

 

Unit D Computer Rooms

Renovation of both rooms is complete and a pre-punch inspection is being performed prior to the rooms being turned-over to the Owner.


Unit E Toilet Rooms
The renovation of girl’s toilet room is on hold until we receive a new exhaust fan for the area.  This is an unforeseen design change.

 

Unit F Elevator

In the process of completing additional requests prior to requesting the State elevator inspection.


Unit G Rooms G106 thru G108

Erection of ceiling grid and light fixtures are complete.  Placement of ceiling tiles will be performed after the overhead inspection.  Placement of flooring and the installation of millwork are scheduled for Monday, March 15th.


Unit J Football Lockers

Demolition is scheduled to start today in this area.

 

Unit J North Toilet Rooms
Pre-punching of the rooms is scheduled to be complete by Thursday of this week in order to facilitate the turn-over to the Owner.


Click here for a printable version of this report.

Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School

Project Overview

 Exterior Skin of the Building (North & South Elevations)Demolition and erection of exterior metal studs & sheathing are complete. We are continuing to erect masonry, EIFS and windows.

Corridors (1st Floor)
-Old ductwork has been removed from the main corridor and is being replaced with new ductwork.
-he main stairs have been removed and the new structural stairs are being erected. Placement of terrazzo will commence after erection.

Unit A - Renovation of the Old Administration Area This area is complete and ready for inspection in regards to generating a punch list.

Unit B - New Science Classrooms
-wo science rooms are being renovated and waiting for casework delivery in order to commence VCT installation.
-ainting of walls and the erection of ceilings are complete.

Units A and C, 2nd Floor, North Section of Building
The East and West classrooms have been turned-over to the Owner for move-in. Carpet is being laid in these rooms. Casework is located on-site.

Unit F - Kitchen Area
All underground installations are complete. The concrete slab has been replaced. The erection of masonry walls is complete. The freezer/cooler curbs have been set. All overhead installations will be complete by July 22nd.

Unit F Cafeteria Area
ll overhead installations are complete. All masonry work is complete.

Unit G - Industrial Art Classrooms (Rooms 106, 107 & 108)
Continue to pull electrical wire from the new electrical switchgear to their designated electrical panels.

Unit J Main / Auxiliary Gymnasiums
The installations that were installed last summer are being painted this summer.

Unit J Existing Athletic Locker Rooms/Athletic Office (East Side of Gymnasium)
We started renovating the Boy's locker room which is the last phase along the East side of the gym.

Schedule

Completion of Phase 1 Complete
Completion of A/B Addition Complete
Transition of Data System Complete
Completion of Data for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor Complete
Commence Phase 4 Work June 2009
Commence Phase 5 Work Started
Completion Date for Phase 3A, 2nd Floor June 2009
Replace North & South Elevations of the 2nd Story Started
Renovation of the Media Center August 2009
Renovation of the Kitchen & Cafeteria Areas August 2009
Replacement of the Main Stairs August 2009
Completion of the Project August 1, 2010


New Clinic Area


Renovation of 2nd Floor Classrooms


Renovated Restrooms on 2nd Floor


Unit J Addition


Installation of Ceilings Within Cafeteria


Erection of Bulkhead within Media Center

For a printable version of this report, click here.
Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

 
Exterior Skin of the Building 
-Along the North elevation, the upper half of the existing skin has been removed and replaced with drywall material.
-2 of 6 bays have been completed along the North elevation.  We will be starting our 3rd bay during the week of May 11th.

         

Unit A – Renovation of the Old Administration Area

Turnover to the Owner is scheduled for June 8th.

Unit A – New Science Classrooms

One of the science rooms has been turned-over to the Owner.

Unit B – New Addition, Science Rooms

Underground plumbing and electrical lines are complete for (3) science classrooms.

 

Units B and D, 2nd Floor, North Section of Building

-Ceiling grid is being erected.  Light fixtures are being placed within the ceiling grid system.  Interior walls are being painted.  Mechanical and electrical finishes are being installed.
-Scheduled to turnover the remaining classrooms June 8th.

Unit F – Loading Dock Area

Cooling towers and (1) of the chillers were activated during the week of May 4th.


Unit G – Industrial Art Classrooms (106, 107 & 108)

-The new air handling unit and new electrical switchgear have been placed in their designated locations at the elevated mechanical deck and hook-ups have commenced.


Unit J Existing Athletic Locker Rooms/Athletic Office (East of Gymnasium)

-The athletic office and trophy room have been renovated and turned-back over to the Owner.
-Working on the renovation of the Girl’s locker rooms.

Units J / K – Elevator / Corridor / Locker Room / Mechanical Addition

-The elevator contractor is nearly complete with the installation of the new elevator.
-Exterior finishes are being erected and finished.


Completion of Phase 1 Complete
Completion of A/B Addition Complete
Transition of Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor Complete
Commence Phase 4 Work June 2009
Commence Phase 5 Work Started
Completion Date for Phase 3A, 2nd Floor June 2009
Replace North & South Elevations on the 2nd Story Started
Renovation of the Media Center August 2009
Renovation of Kitchen/Cafeteria Areas August 2009
Replacement of the Main Stairs August 2009
Completion of the Project August 1, 2010



Re-skinning of the North Elevation


Renovation of the Remaining Classrooms on the 2nd Floor


Unit G, Mechanical Room


New Chiller

Click here for printable version of this report.

Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

 
The overall project is 64% complete.

 
Unit A - Old Administration Area and Unit A - Science Classrooms

Continue to erect interior walls and install mechanical, electrical and plumbing rough-ins.
New masonry walls are complete.

Unit B – New Addition, Science Rooms

Demolition is complete and installation of underground plumbing lines has started.
 

Units B and D, 2nd Floor, North Section of Building

Demolition is complete and we have started installing mechanical and electrical overhead installations.


Unit F – Loading Dock Area

Cooling towers and (1) of the chillers are scheduled to be activated by May 1st.

Unit G – Industrial Art Classrooms (106, 107 & 108)
The elevated mechanical deck has been erected and the slab-on-deck has been placed.  All mechanical / electrical equipment that rest on this deck are located on-site.   

 
Units J / K – Locker Room / Mechanical Addition

A portion of the roofing system was placed during Spring Break.
The elevator contractor has mobilized and has started installation of the new elevator.
All new concrete slabs have been placed with the exception of the entrance to the Athletic Director’s office.

Schedule

Completion of Phase 1 Complete
Completion of A/B Addition Complete
Transition of Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor Complete
Commence Phase 4 Work June 2009
Commence Phase 5 Work Started
Completion Date for Phase 3A, 2nd Floor June 2009
Replace North & South Elevations of the 2-Story August 2009
Renovation of the Media Center August 2009
Renovation of Kitchen & Cafeteria Areas August 2009
Replacement of the Main Stars August 2009
Completion of the Project August 1, 2010

 

Enclosure of Units F and J

Erection of new building skin along south elevation.


Erection of new walls at new administration area.


Interior Finishes at 2nd floor, middle corridor

Click here for printable version.
Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview


The overall project is 61% complete.


Unit A - Old Administration Area and Science Classroom
During the 1st week of March we started demolition work within the old administration area. In addition, we recommenced our work within Unit A science classroom.

 

Unit B – New Addition, Science Rooms

Science classrooms have been turned-over to the Owner for occupancy.

Units B and D, 2nd Floor, Middle Section of Building

The next set of (16) classrooms are scheduled to be turned-over March 13th.

 
Unit F – Loading Dock Area

The new emergency generator was energized this past month. Continuing to route chilled water lines to the cooling towers and chillers.


Unit G – Industrial Art Classrooms (106, 107 & 108)

Demolition and placement of foundations within these classrooms is complete and we are ready for steel erection.

 

Units J / K – Locker Room / Mechanical Addition

Continuing to erect exterior masonry walls.  Placement of floor slabs and setting of mechanical equipment are scheduled to be complete this month.

  Schedule

Completion of Phase I Complete
Completion of A/B Addition Complete
Transition of Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Replace North & South Elevations  of the 2-Story August 2009
Renovation of the Media Center August 2009
Renovation of the Kitchen & Cafeteria Areas August 2009
Replacement of the Main Stairs August 2009
Completion Date for Phase 3, 2nd Floor March 2009
Completion Date for Phase 3A, 2nd Floor June 2009
Commence Phase 4 Work April 2009
Commence Phase 5 Work June 2009
Completion of Project August 1, 2010


New Science Rooms


New Science Rooms

Renovation of 2nd Set of Classrooms


New Locker Rooms/Mechanical Mezzanine Addition

Click here for a printable version of this report.
Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

The overall project is 60% complete and we have expended approximately $22 million dollars.

Unit B - New Addition, Science Rooms
Casework has been installed. Mechanical and electrical hook-ups at each work station are complete.

Units B and D, 2nd Floor, Middle Section of Building
 Interior finishes are proceeding and the turnover date for this phase is early March.

Unit F - Loading Dock Area
New Cooling Towers and Emergency Generator have been set in their permanent location outside the Boiler Room. We are proceeding on infilling existing louver openings and the setting of new louvers.

Unit F - Entrance and Cafeteria Expansion
Placement of exterior Patio Area and sidewalks/steps are complete.

Units J / K - Locker Room / Mechanical Addition
Structural Steel has been erected and detailed. Continuing to erect exterior masonry walls (weather dependant).

Schedule

Completion of Phase I Complete
Completion of A/B Addition Complete
Transition Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor March 2009
Completion Date for Phase 3A, 2nd Floor June 2009
Commence Phase 4 Work April 2009
Commence Phase 5 Work June 2009
Completion of the Project August 1, 2010
















Setting of New Cooling Towers & Generator


Erection of Structural Steel @ Vestibule / Mechanical Room Addition


Placement of Cafeteria Patio and Steps


New Addition - Science Room


Renovation of 2nd Floor Classroom

Click here for printable version.

Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

The overall project is 58% complete and we have expended approximately $22 million dollars. 

Unit A – New Addition, Administration Area
    -Interior Finishes will be complete this week
    -Sprinkler System will be activated on January 14th

Unit B – New Addition, Science Rooms
    -Casework will be installed during the week of January 12th.
    -Mechanical and electrical installations will follow.

Units B and D, 2nd Floor, Middle Section of Building
    -Overhead Rough-Ins are proceeding
    -Drywall bulkheads are being erected
    -Painting has commenced

 Unit E – Main/North Entrance
    -Flooring was completed over Christmas Break

Unit F – Entrance and Cafeteria Expansion
    -Complete the Building Enclosure
    -Work on the Patio Area and future Sidewalks/Steps

Unit J – Gymnasium and Unit K Auxiliary Gymnasium
    -Auxiliary Gym - Acoustical Wall & Ceiling Panels
    -Roof-Top Exhaust Fans are operational
    -New Mechanical Units were placed in the old weight lifting room.

Unit J – Stairs and Elevator Addition
    -Erecting Masonry Exterior Walls

Units J/K – Locker Room / Mechanical Addition
    -Building foundations have been placed

Schedule

Completion of Phase 1     Complete    
Completion of A/B Addition     Complete
Transition of Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor March 2009
Completion Date for Phase 3A, 2nd Floor June 2009
Commence Phase 4 Work April 2009
Commence Phase 5 Work June 2009
Completion of the Project August 1, 2010

Greater Clark County Schools
New Entrance at Bus Parking Lot

Greater Clark County Schools
Erection of Acoustical Panels at Auxiliary Gym

Greater Clark County Schools
Area Outside Cafeteria

Greater Clark County Schools
Setting of New Chillers

Click here for printable version.

Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

The overall project is 53% complete and we have expended approximately $20.2 million dollars.

Units A/B - Addition
    -Interior Finishes
    -Owner Move-In

Units B and D, 2nd Floor, Middle Section of Building
    -Demolition Work

Unit E - Main/North Entrance
    -Storefronts
    -Ceiling Grid Followed by Light Fixtures & Ceiling Pads
    -Flooring

Unit F - Entrance and Cafeteria Expansion
    -Building Enclosure
    -Overhead Rough-Ins

Unit J - Gymnasium and Unit K Auxiliary Gymnasium
    -Auxiliary Gym - Acoustical Wall & Ceiling Panels
    -Air Handling Units

Unit J - Stairs and Elevator Addition
    -Elevator Shaft
    -Erecting Masonry Exterior Walls

 Schedule

Completion of Phase 1     December 2008
Completion of A/B Addition                        December 2008
Transition of Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor March 2009
Completion Date for Phase 3A, 2nd Floor June 2009
Commence Phase 4 Work April 2009
Commence Phase 5 Work June 2009
Completion of the Project August 1, 2010

 

Greater Clark County Schools
New Administration Area

 

Greater Clark County Schools
Construction of New Science Lab

 

Greater Clark County Schools
Construction of New Elevator/Stairs Addition

 

Greater Clark County Schools
Construction of New South Entrance

 

Greater Clark County Schools
New Entrance at Bus Drop-Off

 

Greater Clark County Schools
Newly Renovated 2nd Floor Corridors

Click here for printable version.

Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

The overall project is 49% complete and we have expended approximately $18.5 million dollars. 

Units A/B - Addition
Installation of the metal roofing system at the main entrance and at the North and South entrances continues.  Ceiling grid and light fixtures have been erected in Unit A and we continue to work in Unit B.  The setting of casework is scheduled for November 11th.  Storefronts will be erected during the week of November 3rd thus allowing us to heat the new addition.  We are still scheduled to turnover this area to the Owner during Christmas Break, thus allowing construction trades to occupy the old administration area.

Units B and D, 2nd Floor
This area was completed and turned-over to the Owner for their use.  Sixteen classrooms will be transitioned from the middle section of the 2nd floor into the newly renovated classrooms.

Unit E – Main Entrance
A temporary enclosure has been erected in order to complete the interior finishes within the entrance.  Once the storefronts are complete at Units A/B addition, Unit E will be erected.

Unit F – Entrance and Cafeteria Expansion
The mechanical hook-ups to the new Air Handling Units are nearly complete.  In addition, the pulling of electrical wire and final terminations to the new switchgear will be completed this month.

Unit J – Gymnasium and Unit K Auxiliary Gymnasium
We have started erecting acoustical wall panels within the Auxiliary Gym and the completion of the panels will be performed over Christmas Break.

Unit J – Stairs and Elevator Addition
Concrete foundations will be complete by the middle of November.  Masonry contractor is scheduled to remobilize on November 10th to start erecting masonry at this location.  Elevator casing was drilled in early November.

  Schedule

Completion of Phase I   

December 2008

Completion of A/B Addition

December 2008
Transition of Data System Complete
Completion Date for Phase 2, 2nd Floor    Complete
Completion Date for Phase 3, 2nd Floor January 2009
Completion Date for Phase 3A, 2nd Floor April 2009
Commence Phase 4 Work April 2009
Commence Phase 5 Work June 2009
Completion of Project     August 1, 2010


Unit F Entrance and Cafeteria Addition


Erection of Interior Finishes at Unit F Entrance

 
Placement of Foundations at Stairway and Elevator Addition


2nd Floor Finishes


Erection of Ceilings and Lights at New Administration Area


Energizing of New Boilers

Click here for printable version.

Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

The overall project is 44% complete and we have expended approximately $13 million dollars.  The existing roof elevations have been re-roofed with the exception of the 2-story building, thus solving a vast majority of the roof leaks within the building.  Also, a portion of the building is running off the new electrical transformers which were set and energized this past summer.  On October 17th, one of the old transformers will be decommissioned and electrical feeders will be transferred to one of the new transformers.

The new boilers, pumps and water heaters are energized and operational.  The new gas service and meters have been set and are waiting for final transition from the building to the new meter which will be performed on October 17th.  Several classrooms were renovated during the summer months and are being utilized as temporary classrooms while a Southern portion of the 2nd floor is being renovated.

Units A/B - Addition
Erection of exterior and interior masonry is complete.  Interior metal studs and drywall have been erected in Unit A.  Overhead rough-ins for mechanical, electrical and fire protection are approximately 90% complete.  Installation of exterior windows and placement of the roofing system are complete.  Aluminum storefronts will be erected during the month of October.  We are scheduled to turnover this area to the Owner during Christmas Break thus allowing construction trades to occupy the old administration area.

Units B and D, 2nd Floor
Erection of mechanical/electrical overhead rough-ins and the installation of ceiling grid are complete.  Light fixtures are being set within the grid system.  Re-setting of the toilet fixtures in order to meet ADA requirements is complete.  Painting of the classrooms, restrooms and corridor is complete.  Placement of floor finishes has commenced.

Unit E – Main Entrance
The placement of the roofing system, installation of the exterior windows and placement of the EIFS system are complete.  Interior bulkheads have been erected and the installation of the ductwork within the bulkheads is complete.  Overhead and wall rough-ins for electrical rough-ins are complete.  New storefronts will be erected during the month of October thus allowing the installation of interior finishes.

Unit F – Entrance and Cafeteria Expansion
The erection of structural steel and the placement of the concrete slabs are complete for the new entrance and cafeteria expansion.  Erection of metal stud framing and masonry continues along the exterior skin of the building.  The new air handling units and electrical switchgear units have been placed on the mezzanine level and are currently being hooked-up.  Placement of the roofing system is scheduled to commence during the 2nd week of October.

Unit J – Gymnasium and Unit K Auxiliary Gymnasium
The re-routing of roof drains, erecting of new ductwork and the erection of new sprinkler lines are complete.  Installation of new acoustical panels in the Auxiliary Gym is scheduled for Christmas Break.  The expansion of the mezzanine decks within the (2) mechanical rooms continues and is expected to be completed this month.

Exterior Shell of the Building
The erection of the Exterior Insulation Finish System (EIFS) is complete along the East and West elevations of the 2-story building.  The overall placement of the roofing system is 90% complete which is ahead of schedule.  Exterior windows are being installed along the East and West elevations of the 2-story building.

Schedule

Completion of Phase 1   

December 31, 2008
Completion of A/B Addition December 31, 2008
Transition of Data System Complete
Commence Phase 2Work January 2009
Commence Phase 3 Work June 2009
Commence 4 Work August 2009
Commence Phase 5 Work February 2010
Completion of the Project     August 1, 2010

 

 
Placement of Exerior Insulation & Finish Systems (EIFS)

 


Unit E Exterior Finish and Placement of New Roofing System

 


Construction of Unit F Entrance and Cafeteria Expansion

 


Installation of Drywall at Unit A Addition

 


Erection of Mechanical/Electrical Lines at Cafeteria Expansion

 


Units B & D, 2nd Floor, Installation of Overhead Finishes

 


Units B & D, 2nd Floor, Classroom Finishes

 


Placement of Foundations at Unit J Elevation/Stairs Addition

 

Click here for printable version.

 

Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

Units A/B - Addition
Erection of structural steel and erection of exterior masonry are nearing completion.  Placement of floor slabs is complete.  Erection of metal stud framing along the East elevation of the existing building will be complete by Tuesday, August 6th thus allowing the placement of the roofing system.

Unit A – Future Science Classrooms
All underground rough-ins are complete and the placement of the floor slabs is scheduled for Thursday, August 8th.

Units B and D, 2nd Floor
Demolition is complete.  Erection of mechanical/electrical overhead rough-ins continued.  Masonry patching, masonry in-fills and erection of new masonry walls are complete.

Unit C – Future Science Classrooms Renovation
Erection of ceiling grid and placement of new light fixtures are progressing and will be operational for the start of school.  Casework has been delivered and will be set prior to the start of school.

Unit D - Classroom Renovation
Ceiling systems are being erected within the room.

Unit E - Future MDF Room
The transition of the data system occurred last month as scheduled.  The ceiling system and placement of the remaining VCT will occur this month.

Unit E – Main Entrance
Structural steel has been erected and erection of parapet wall has commenced.  New entrances to the Media Center have occurred.  This entrance will be utilized by the students and staff for the start of school.

Unit F – Entrance
Building foundations have been poured and placement of the floor slab is scheduled for Monday, August 5th.  Steel erection will commence after the slab placement.  This entrance will be utilized by the students and staff for the start of school.

Boiler Room
The new electrical switchgear and exterior transformers were energized during the month of July.  In addition, the gas company has routed their new gas line to the new gas meter.  The mechanical contractor is scheduled to route his line from the meter to inside the building prior to the start of school.

Unit J – Gymnasium
The new mechanical units have been set and erection of new mechanical ductwork is complete.  New sprinkler piping has been erected outside the mechanical rooms.

Exterior Shell of the Building
The EIFS system is currently being erected along the West elevation and they will proceed to the East elevation once they are complete with the West elevation.  A new roofing system has been placed on 90% of the existing roof system. 

Schedule

Completion of Phase 1 December 31, 2008
Completion of A/B Addition December 31, 2008
Transition of Data System Complete
Commence Phase 2 Work January 2009
Commence Phase 3 Work June 2009
Commence Phase 4 Work August 2009
Commence Phase 5 Work February 2010
Completion of the Project August 1, 2010

Greater Clark blog
New main entrance

Greater Clark Construction blog
Erection of new dictwork within main gymnasium

Greater Clark blog
Building foundations at cafeteria expansion

Greater Clark Construction blog
New exterior skin along west elevation

Greater Clark Construction blog
New entrance to unit E

Greater Clark blog
Installation of EIFS along west elevation

Click here for printable version.

Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

Units A/B - Addition
Foundations are complete and facebrick is being erected on the exterior skin of the building.  Mechanical and electrical underground continue to be placed within the building footprint.  Placement of floor slabs is scheduled for July 2nd and 7th.  Erection of remaining structural steel will commence subsequent to the placement of slabs.

Unit A – Future Science Classrooms
Demolition is complete and the General Contractor is proceeding on foundations.

Units B and D, 2nd Floor
Demolition of carpeting is complete in the classrooms and the only areas that remain are the corridors.  Overhead and wall rough-ins continue.

Unit C – Future Science Classrooms Renovation
Underground installations are complete.  Placement of slab is scheduled for July 7th.

Unit D - Classroom Renovation
Masonry walls are being painted and overhead installations continue to be erected.

Unit E - Future MDF Room
Interior walls have been painted and the placement of the flooring system is complete.  MDF equipment will be set on July 3rd.  This room is expected to be turned-over to the Owner during the 2nd week of July. 

Unit E – Main Entrance
Demolition and steel erection is complete.  During the week of June 30th, the underground plumbing line will be installed.

Unit F – Entrance
Building foundations have been determined and excavation of foundations is expected to commence the first week of July.

Unit F - Boiler Room
Back-filling and the placement of underground plumbing is complete within the  recessed area of the boiler room.  Slab placement will be performed during the 2nd week of July.

Electrical switchgear is set and the electrical wire has been pulled from the switchgear to the exterior location of the new transformers.  Duke Energy has approved this installation and will proceed on installing their feeders from the transformers to the street location.

Unit J – Gymnasium
Demolition of the ductwork system is complete and erection of the new spiral ductwork has started.  Erection of the sprinkler system is complete for this area with the exception of the mechanical rooms. 

Exterior Shell of the Building
The removal of the exterior facebrick and masonry block at the West elevation of the 2-story building is complete.  Parapet wall is being constructed along this elevation.  General contractor is proceeding with the removal of the exterior skin along the South elevation. 

Roof Level
Placement of the new roofing system is approximately 50% complete. 

Site Work
As of June 30th, the gas company started the installation of the new gas line from Allison Lane to the new location of the meter.  The setting of new meter(s) and the removal of the old meters will be complete prior to the start of school in the Fall.

Schedule

Completion of Phase 1 December 31, 2008
Completion of A/B Addition December 31, 2008
Completion of Unit E, MDF Room July 3, 2008
Commence Phase 2 Work January 2009
Commence Phase 3 Work June 2009
Commence Phase 4 Work August 2009
Commence Phase 5 Work February 2010
Completion of the Project August 1, 2010

Click here for printable version.

Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

Units A/B - Addition 
Placement of foundations is nearly complete.  Majority of the structural steel is set with exception of the metal joists and decking.  Exterior masonry walls are being erected.  Mechanical and electrical underground continue to be placed within the building footprint in order to place the new concrete floors.

Unit J - Elevator/Stairs Addition
Topsoil has been removed, demolition has been completed and a temporary fence has been erected in order to isolate this area from students.  Placement of elevator foundations is being held-up due to an unforeseen storm line which is lying within our new building foundations.

Boiler Room
One of the existing chillers has been relocated and reconnected at its temporary location.  The old chiller and boilers have been removed from the building.  We are in the process of back-filling the recess area of the boiler room in order to pour a new concrete slab at the same elevation as the surrounding slabs.

The new boilers and pumps have been set and pipe connection to the mechanical units is complete. 

Unit A – Future Science Classrooms
As of June 4th, we started demolition activities within this classroom which will be followed by new foundations.

Unit C – Future Science Classrooms Renovation
Demolition activities and the placement of concrete are complete.  We are currently working on erecting structural steel within this classroom.    

Unit D - Classroom Renovation
Demolition activities, erection of structural steel, placement of concrete and erection of masonry walls are complete.  We are currently erecting new overhead installations within these classrooms.    

Unit E - Future MDF Room
Currently the Owner’s computer equipment has been relocated out of these rooms.  The demolition activities and the erection of interior walls are complete.  Painting is scheduled to start during the week of June 9th.   Once the flooring and painting are complete, the new MDF equipment will be set and terminated.

Unit E – Main Entrance
Started demolition activities at this building entrance and at the adjacent classroom. 

Units B and D, 2nd Floor
We have started the demolition activities for the 2nd floor classrooms.

Exterior Shell of the Building
We have started the removal of exterior facebrick and masonry block at the West elevation of the 2-story building followed immediately with the installation of new metal studs and drywall.

Roof Level
Existing chimney stack has been demolished to the roof level.  Roofing contractor continues to vacuum/remove all the loose rock from the various roof levels.  Application of the roofing system has commenced at the West elevation of the building and will proceed to the East elevation.

Site Work
The feeder conduit from the new electrical transformers to the new switchgear location has been installed.  The placement of the new transformer pads is complete and installation of the feeder conduit to Allison Lane is complete.  The new transformers that were furnished by Duke Energy have been set and will be energized once the electrical feeds have been installed from the interior switchgear to the new transformers.

 Greater Clark blog
Erection of exterior walls and structural steel at Units A/B

Greater Clark blog
Removal of main entrance tunnel

Greater Clark blog
Erection of new skin along west elevation

Greater Clark blog
Demolition of Unit E entrance

Greater Clark blog
Erection of masonry at Unit C science classroom

Greater Clark blog
Demolition of HVAC at gymnasium

 

Click here for printable version. 

Email thisemail | permalinkpermalink
Posted by Jamie Hergott

Jeffersonville High School Project Overview

 Units A/B - Addition
Placement of foundations is nearly complete and erection of structural steel is scheduled to commence during the week of May 12th.  The mason continues to place foundation block.  Backfilling of new foundations have started.

 Unit J - Elevator/Stairs Addition
Topsoil has been removed, demolition has been completed and a temporary fence has been erected in order to isolate this area from students.  Excavation for elevator foundations will commence during the week of May 12th.

 Boiler Room
One of the existing chillers has been relocated and reconnected at its temporary location.  The other chiller and boilers have been removed from the building.  We are in the process of back-filling the recess area of the boiler room in order to pour a new concrete slab at the same elevation as the surrounding slabs.

The new boilers have been set and pipe connection to the units is complete.  Boiler pumps are being delivered and set on their housekeeping pads.

 Unit E - Future MDF Room (Main Distribution Frame)
Currently the Owner’s computer equipment has been relocated out of these rooms.  Erection of temporary partitions and demolition activities will be completed by the end of the month.

 Unit D - Classroom Renovation
Demolition within this classroom has been completed, structural steel has been erected and backfilling of the area is complete.  Placement of concrete is scheduled for the week of May 12th.

Unit C - Science Classroom Renovation
Demolition within this classroom is nearly complete.  Saw-cutting and removal of existing slab for future foundations has started.

Roof Level
Existing chimney stack has been demolished to the roof level.  Roofing contractor is preparing to vacuum/remove all the loose rock from the roof level.  Once this is complete, the roofing system will be installed from the West direction to the East portion of the building.

Site Work
The feeder conduit from the new electrical transformers to the new switchgear location has been installed.  The placement of the new transformer pads is complete and installation of the feeder conduit to Allison Lane is complete.  We are now waiting on Duke Energy to set their new transformers and set a new utility pole along Allison Lane.

Click here for printable version.

Email thisemail | permalinkpermalink

7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS