Jeffersonville High School Project Overview
Areas that have been renovated and turned-back over to the Owner:
-Replacement of the Exterior Skin of the Building along the North & South elevations. -Removal of the old ductwork system and replacement with new installations on the 1st floor corridors. -Main stairs have been removed and the new stairs have been erected. Majority of the finishes are complete with exception of the handrails. -Old Administration Area has been converted into a new Clinic Area and Guidance Offices. -Two existing science classrooms have been renovated. - Units A and D, 2nd Floor, North and South Classrooms have been completed. -Kitchen and Cafeteria Areas have been completely renovated. -New Media Center is complete. -Structural steel has been erected at the North and South entrances and final building finishes have been erected. -Placement of the new Dumpster Area outside the Kitchen Area is complete. -Painting of new installations within the Main and Auxiliary Gyms is complete.
Work continues at the following Areas:
-Renovation of 1st Floor, Science Classrooms and old Guidance Offices that were located along the South and West elevations of the 2-Story portion of the building. -Renovation of 1st Floor classrooms that are located along the North and West elevations. -Completion of (4) restrooms (1st & 2nd floors) next to the main stairs. -Renovation of Boys PE Locker Rooms continues. -Elevator and Stairs Addition continues. -Unit K, Locker Room Addition continues. -Unit G, Industrial Technology Area, pulling electrical wire from the switchgear to various electrical panels.
Schedule
|
Phase 1
|
Complete
|
|
A/B Addition
|
Complete
|
|
Transition of Data System
|
Complete
|
| Phase 2, 2nd Floor |
Complete
|
|
Phase 3, 2nd Floor
|
Complete
|
|
Phase 3A, 2nd Floor
|
Complete
|
|
Replace North & South Elevations of 2nd Story
|
Complete
|
|
Renovation of the Media Center
|
Complete
|
|
Renovation of the Kitchen & Cafeteria Areas
|
Complete
|
|
Commence Phase 4 Work
|
Started
|
|
Commence Phase 5 Work
|
Started
|
|
Replacement of the Main Stairs
|
Started
|
|
Completion of the Project
|
August 1, 2010 |
Click here for a printable version of this report.
Schedule
| Phase 2, 1st Floor |
|
| New Restrooms at Main Stars |
Completed |
| Wrestling Locker Room |
December 2009 |
| Phase 3, Unit G |
|
| Phase 1 |
December 2009 |
| Phase 2 |
April 2010 |
| Phase 3 |
July 2010 |
| Phase 4, 1st Floor |
|
| North & West Classroom |
December 2009 |
| Unit J, Elevator/Addition |
January 2010 |
| Phase 5, 1st Floor |
|
| South Science Rooms (3 Total) |
December 2009 |
| Softball Locker Room |
January 2010 |
| Gym Vestibule and Adj. Restrooms |
January 2010 |
| New Computer Rooms |
January 2010 |
| West Science Room & Life Skills |
January 2010 |
| 3 Interior Science Rooms |
April 2010 |
| Auditorium Restrooms |
July 2010 |
| Unit E, Corridor Restrooms |
July 2010 |
| Ceiling and Floor @ Corridors |
July 2010 |
| Completion of the Project |
August 1, 2010 |
Click here for printable version of this report.
Jeffersonville High School Project Overview
As of December, 2009, the overall project is 92% complete and we have expended approximately $35.1 million dollars.
Units A-D, 1st Floor Corridors
In regards to the North side of the 2-story portion of the building, the new ceiling grid and light fixtures have been erected. Twenty (20%) percent of the VCT tile has been laid.
Also, the erection of ceilings on the Southern portion of the building has commenced. Currently the contractor has started at Unit D and is proceeding eastward.
Unit B Science Classrooms
Demolition of the interior classrooms has begun.
Unit D Science Room, Moderate Classrooms and Life Skills Lab
The perimeter classrooms along the Southern and Western elevations of the 2-story portion of the building have been turned-over to the Owner and are being occupied by teachers and students.
Unit D Renovation of Old Bookstore Area
The interior walls have been erected. Walls and overhead rough-ins are complete.
Unit D Computer Rooms
Renovation of both rooms is complete and a pre-punch inspection is being performed prior to the rooms being turned-over to the Owner.
Unit E Toilet Rooms The renovation of girl’s toilet room is on hold until we receive a new exhaust fan for the area. This is an unforeseen design change.
Unit F Elevator
In the process of completing additional requests prior to requesting the State elevator inspection.
Unit G Rooms G106 thru G108
Erection of ceiling grid and light fixtures are complete. Placement of ceiling tiles will be performed after the overhead inspection. Placement of flooring and the installation of millwork are scheduled for Monday, March 15th.
Unit J Football Lockers
Demolition is scheduled to start today in this area.
Unit J North Toilet Rooms Pre-punching of the rooms is scheduled to be complete by Thursday of this week in order to facilitate the turn-over to the Owner.
Click here for a printable version of this report.
Jeffersonville High School
Project Overview
Exterior Skin of the Building (North & South Elevations)Demolition and erection of exterior metal studs & sheathing are complete. We are continuing to erect masonry, EIFS and windows.
Corridors (1st Floor) -Old ductwork has been removed from the main corridor and is being replaced with new ductwork. -he main stairs have been removed and the new structural stairs are being erected. Placement of terrazzo will commence after erection.
Unit A - Renovation of the Old Administration Area This area is complete and ready for inspection in regards to generating a punch list.
Unit B - New Science Classrooms -wo science rooms are being renovated and waiting for casework delivery in order to commence VCT installation. -ainting of walls and the erection of ceilings are complete.
Units A and C, 2nd Floor, North Section of Building The East and West classrooms have been turned-over to the Owner for move-in. Carpet is being laid in these rooms. Casework is located on-site.
Unit F - Kitchen Area All underground installations are complete. The concrete slab has been replaced. The erection of masonry walls is complete. The freezer/cooler curbs have been set. All overhead installations will be complete by July 22nd.
Unit F Cafeteria Area ll overhead installations are complete. All masonry work is complete.
Unit G - Industrial Art Classrooms (Rooms 106, 107 & 108) Continue to pull electrical wire from the new electrical switchgear to their designated electrical panels.
Unit J Main / Auxiliary Gymnasiums The installations that were installed last summer are being painted this summer.
Unit J Existing Athletic Locker Rooms/Athletic Office (East Side of Gymnasium) We started renovating the Boy's locker room which is the last phase along the East side of the gym.
Schedule
| Completion of Phase 1 |
Complete |
| Completion of A/B Addition |
Complete |
| Transition of Data System |
Complete |
| Completion of Data for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
Complete
|
| Commence Phase 4 Work |
June 2009 |
| Commence Phase 5 Work |
Started |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Replace North & South Elevations of the 2nd Story |
Started |
| Renovation of the Media Center |
August 2009 |
| Renovation of the Kitchen & Cafeteria Areas |
August 2009 |
| Replacement of the Main Stairs |
August 2009 |
| Completion of the Project |
August 1, 2010 |
|
|
New Clinic Area
 Renovation of 2nd Floor Classrooms
Renovated Restrooms on 2nd Floor
Unit J Addition
Installation of Ceilings Within Cafeteria
Erection of Bulkhead within Media CenterFor a printable version of this report, click here.
Jeffersonville High School Project Overview
Exterior Skin of the Building -Along the North elevation, the upper half of the existing skin has been removed and replaced with drywall material. -2 of 6 bays have been completed along the North elevation. We will be starting our 3rd bay during the week of May 11th.
Unit A – Renovation of the Old Administration Area
Turnover to the Owner is scheduled for June 8th.
Unit A – New Science Classrooms
One of the science rooms has been turned-over to the Owner.
Unit B – New Addition, Science Rooms
Underground plumbing and electrical lines are complete for (3) science classrooms.
Units B and D, 2nd Floor, North Section of Building
-Ceiling grid is being erected. Light fixtures are being placed within the ceiling grid system. Interior walls are being painted. Mechanical and electrical finishes are being installed. -Scheduled to turnover the remaining classrooms June 8th.
Unit F – Loading Dock Area
Cooling towers and (1) of the chillers were activated during the week of May 4th.
Unit G – Industrial Art Classrooms (106, 107 & 108)
-The new air handling unit and new electrical switchgear have been placed in their designated locations at the elevated mechanical deck and hook-ups have commenced.
Unit J Existing Athletic Locker Rooms/Athletic Office (East of Gymnasium)
-The athletic office and trophy room have been renovated and turned-back over to the Owner. -Working on the renovation of the Girl’s locker rooms.
Units J / K – Elevator / Corridor / Locker Room / Mechanical Addition
-The elevator contractor is nearly complete with the installation of the new elevator. -Exterior finishes are being erected and finished.
| Completion of Phase 1 |
Complete |
| Completion of A/B Addition |
Complete |
| Transition of Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
Complete |
| Commence Phase 4 Work |
June 2009 |
| Commence Phase 5 Work |
Started |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Replace North & South Elevations on the 2nd Story |
Started |
| Renovation of the Media Center |
August 2009 |
| Renovation of Kitchen/Cafeteria Areas |
August 2009 |
| Replacement of the Main Stairs |
August 2009 |
| Completion of the Project |
August 1, 2010 |
 Re-skinning of the North Elevation
 Renovation of the Remaining Classrooms on the 2nd Floor
 Unit G, Mechanical Room
 New Chiller
Click here for printable version of this report.
Jeffersonville High School Project Overview
The overall project is 64% complete.
Unit A - Old Administration Area and Unit A - Science Classrooms
Continue to erect interior walls and install mechanical, electrical and plumbing rough-ins. New masonry walls are complete.
Unit B – New Addition, Science Rooms
Demolition is complete and installation of underground plumbing lines has started.
Units B and D, 2nd Floor, North Section of Building
Demolition is complete and we have started installing mechanical and electrical overhead installations.
Unit F – Loading Dock Area
Cooling towers and (1) of the chillers are scheduled to be activated by May 1st.
Unit G – Industrial Art Classrooms (106, 107 & 108) The elevated mechanical deck has been erected and the slab-on-deck has been placed. All mechanical / electrical equipment that rest on this deck are located on-site.
Units J / K – Locker Room / Mechanical Addition
A portion of the roofing system was placed during Spring Break. The elevator contractor has mobilized and has started installation of the new elevator. All new concrete slabs have been placed with the exception of the entrance to the Athletic Director’s office.
Schedule
| Completion of Phase 1 |
Complete |
| Completion of A/B Addition |
Complete |
| Transition of Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
Complete |
| Commence Phase 4 Work |
June 2009 |
| Commence Phase 5 Work |
Started |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Replace North & South Elevations of the 2-Story |
August 2009 |
| Renovation of the Media Center |
August 2009 |
| Renovation of Kitchen & Cafeteria Areas |
August 2009 |
| Replacement of the Main Stars |
August 2009 |
| Completion of the Project |
August 1, 2010 |
 Enclosure of Units F and J

Erection of new building skin along south elevation.
Erection of new walls at new administration area.
Interior Finishes at 2nd floor, middle corridor
Click here for printable version.
Jeffersonville High School Project Overview
The overall project is 61% complete.
Unit A - Old Administration Area and Science Classroom During the 1st week of March we started demolition work within the old administration area. In addition, we recommenced our work within Unit A science classroom.
Unit B – New Addition, Science Rooms
Science classrooms have been turned-over to the Owner for occupancy.
Units B and D, 2nd Floor, Middle Section of Building
The next set of (16) classrooms are scheduled to be turned-over March 13th.
Unit F – Loading Dock Area
The new emergency generator was energized this past month. Continuing to route chilled water lines to the cooling towers and chillers.
Unit G – Industrial Art Classrooms (106, 107 & 108)
Demolition and placement of foundations within these classrooms is complete and we are ready for steel erection.
Units J / K – Locker Room / Mechanical Addition
Continuing to erect exterior masonry walls. Placement of floor slabs and setting of mechanical equipment are scheduled to be complete this month.
Schedule
| Completion of Phase I |
Complete |
| Completion of A/B Addition |
Complete |
| Transition of Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Replace North & South Elevations of the 2-Story |
August 2009 |
| Renovation of the Media Center |
August 2009 |
| Renovation of the Kitchen & Cafeteria Areas |
August 2009 |
| Replacement of the Main Stairs |
August 2009 |
| Completion Date for Phase 3, 2nd Floor |
March 2009 |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Commence Phase 4 Work |
April 2009 |
| Commence Phase 5 Work |
June 2009 |
| Completion of Project |
August 1, 2010 | New Science Rooms
New Science Rooms
 Renovation of 2nd Set of Classrooms
New Locker Rooms/Mechanical Mezzanine Addition Click here for a printable version of this report.
Jeffersonville High School Project Overview
The overall project is 60% complete and we have expended approximately $22 million dollars.
Unit B - New Addition, Science Rooms Casework has been installed. Mechanical and electrical hook-ups at each work station are complete.
Units B and D, 2nd Floor, Middle Section of Building Interior finishes are proceeding and the turnover date for this phase is early March.
Unit F - Loading Dock Area New Cooling Towers and Emergency Generator have been set in their permanent location outside the Boiler Room. We are proceeding on infilling existing louver openings and the setting of new louvers.
Unit F - Entrance and Cafeteria Expansion Placement of exterior Patio Area and sidewalks/steps are complete.
Units J / K - Locker Room / Mechanical Addition Structural Steel has been erected and detailed. Continuing to erect exterior masonry walls (weather dependant).
Schedule
| Completion of Phase I |
Complete |
| Completion of A/B Addition |
Complete |
| Transition Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
March 2009 |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Commence Phase 4 Work |
April 2009 |
| Commence Phase 5 Work |
June 2009 |
| Completion of the Project |
August 1, 2010 | Setting of New Cooling Towers & Generator
 Erection of Structural Steel @ Vestibule / Mechanical Room Addition
 Placement of Cafeteria Patio and Steps
 New Addition - Science Room
 Renovation of 2nd Floor Classroom
Click here for printable version.
Jeffersonville High School Project Overview
The overall project is 58% complete and we have expended approximately $22 million dollars.
Unit A – New Addition, Administration Area -Interior Finishes will be complete this week -Sprinkler System will be activated on January 14th
Unit B – New Addition, Science Rooms -Casework will be installed during the week of January 12th. -Mechanical and electrical installations will follow.
Units B and D, 2nd Floor, Middle Section of Building -Overhead Rough-Ins are proceeding -Drywall bulkheads are being erected -Painting has commenced
Unit E – Main/North Entrance -Flooring was completed over Christmas Break
Unit F – Entrance and Cafeteria Expansion -Complete the Building Enclosure -Work on the Patio Area and future Sidewalks/Steps
Unit J – Gymnasium and Unit K Auxiliary Gymnasium -Auxiliary Gym - Acoustical Wall & Ceiling Panels -Roof-Top Exhaust Fans are operational -New Mechanical Units were placed in the old weight lifting room.
Unit J – Stairs and Elevator Addition -Erecting Masonry Exterior Walls
Units J/K – Locker Room / Mechanical Addition -Building foundations have been placed
Schedule
| Completion of Phase 1 |
Complete |
| Completion of A/B Addition |
Complete |
| Transition of Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
March 2009 |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Commence Phase 4 Work |
April 2009 |
| Commence Phase 5 Work |
June 2009 |
| Completion of the Project |
August 1, 2010 |
 New Entrance at Bus Parking Lot
 Erection of Acoustical Panels at Auxiliary Gym
 Area Outside Cafeteria
 Setting of New Chillers
Click here for printable version.
Jeffersonville High School Project Overview
The overall project is 53% complete and we have expended approximately $20.2 million dollars.
Units A/B - Addition -Interior Finishes -Owner Move-In
Units B and D, 2nd Floor, Middle Section of Building -Demolition Work
Unit E - Main/North Entrance -Storefronts -Ceiling Grid Followed by Light Fixtures & Ceiling Pads -Flooring
Unit F - Entrance and Cafeteria Expansion -Building Enclosure -Overhead Rough-Ins
Unit J - Gymnasium and Unit K Auxiliary Gymnasium -Auxiliary Gym - Acoustical Wall & Ceiling Panels -Air Handling Units
Unit J - Stairs and Elevator Addition -Elevator Shaft -Erecting Masonry Exterior Walls
Schedule
| Completion of Phase 1 |
December 2008 |
| Completion of A/B Addition |
December 2008 |
| Transition of Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
March 2009 |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Commence Phase 4 Work |
April 2009 |
| Commence Phase 5 Work |
June 2009 |
| Completion of the Project |
August 1, 2010 |
 New Administration Area
 Construction of New Science Lab
 Construction of New Elevator/Stairs Addition
 Construction of New South Entrance
 New Entrance at Bus Drop-Off
 Newly Renovated 2nd Floor Corridors
Click here for printable version.
Jeffersonville High School Project Overview
The overall project is 49% complete and we have expended approximately $18.5 million dollars.
Units A/B - Addition Installation of the metal roofing system at the main entrance and at the North and South entrances continues. Ceiling grid and light fixtures have been erected in Unit A and we continue to work in Unit B. The setting of casework is scheduled for November 11th. Storefronts will be erected during the week of November 3rd thus allowing us to heat the new addition. We are still scheduled to turnover this area to the Owner during Christmas Break, thus allowing construction trades to occupy the old administration area.
Units B and D, 2nd Floor This area was completed and turned-over to the Owner for their use. Sixteen classrooms will be transitioned from the middle section of the 2nd floor into the newly renovated classrooms.
Unit E – Main Entrance A temporary enclosure has been erected in order to complete the interior finishes within the entrance. Once the storefronts are complete at Units A/B addition, Unit E will be erected.
Unit F – Entrance and Cafeteria Expansion The mechanical hook-ups to the new Air Handling Units are nearly complete. In addition, the pulling of electrical wire and final terminations to the new switchgear will be completed this month.
Unit J – Gymnasium and Unit K Auxiliary Gymnasium We have started erecting acoustical wall panels within the Auxiliary Gym and the completion of the panels will be performed over Christmas Break.
Unit J – Stairs and Elevator Addition Concrete foundations will be complete by the middle of November. Masonry contractor is scheduled to remobilize on November 10th to start erecting masonry at this location. Elevator casing was drilled in early November.
Schedule
|
Completion of Phase I |
December 2008 |
|
Completion of A/B Addition |
December 2008 |
| Transition of Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
January 2009 |
| Completion Date for Phase 3A, 2nd Floor |
April 2009 |
| Commence Phase 4 Work |
April 2009 |
| Commence Phase 5 Work |
June 2009 |
| Completion of Project |
August 1, 2010 |
 Unit F Entrance and Cafeteria Addition
 Erection of Interior Finishes at Unit F Entrance
 Placement of Foundations at Stairway and Elevator Addition
 2nd Floor Finishes
 Erection of Ceilings and Lights at New Administration Area
 Energizing of New Boilers
Click here for printable version.
Jeffersonville High School Project Overview
The overall project is 44% complete and we have expended approximately $13 million dollars. The existing roof elevations have been re-roofed with the exception of the 2-story building, thus solving a vast majority of the roof leaks within the building. Also, a portion of the building is running off the new electrical transformers which were set and energized this past summer. On October 17th, one of the old transformers will be decommissioned and electrical feeders will be transferred to one of the new transformers.
The new boilers, pumps and water heaters are energized and operational. The new gas service and meters have been set and are waiting for final transition from the building to the new meter which will be performed on October 17th. Several classrooms were renovated during the summer months and are being utilized as temporary classrooms while a Southern portion of the 2nd floor is being renovated.
Units A/B - Addition Erection of exterior and interior masonry is complete. Interior metal studs and drywall have been erected in Unit A. Overhead rough-ins for mechanical, electrical and fire protection are approximately 90% complete. Installation of exterior windows and placement of the roofing system are complete. Aluminum storefronts will be erected during the month of October. We are scheduled to turnover this area to the Owner during Christmas Break thus allowing construction trades to occupy the old administration area.
Units B and D, 2nd Floor Erection of mechanical/electrical overhead rough-ins and the installation of ceiling grid are complete. Light fixtures are being set within the grid system. Re-setting of the toilet fixtures in order to meet ADA requirements is complete. Painting of the classrooms, restrooms and corridor is complete. Placement of floor finishes has commenced.
Unit E – Main Entrance The placement of the roofing system, installation of the exterior windows and placement of the EIFS system are complete. Interior bulkheads have been erected and the installation of the ductwork within the bulkheads is complete. Overhead and wall rough-ins for electrical rough-ins are complete. New storefronts will be erected during the month of October thus allowing the installation of interior finishes.
Unit F – Entrance and Cafeteria Expansion The erection of structural steel and the placement of the concrete slabs are complete for the new entrance and cafeteria expansion. Erection of metal stud framing and masonry continues along the exterior skin of the building. The new air handling units and electrical switchgear units have been placed on the mezzanine level and are currently being hooked-up. Placement of the roofing system is scheduled to commence during the 2nd week of October.
Unit J – Gymnasium and Unit K Auxiliary Gymnasium The re-routing of roof drains, erecting of new ductwork and the erection of new sprinkler lines are complete. Installation of new acoustical panels in the Auxiliary Gym is scheduled for Christmas Break. The expansion of the mezzanine decks within the (2) mechanical rooms continues and is expected to be completed this month.
Exterior Shell of the Building The erection of the Exterior Insulation Finish System (EIFS) is complete along the East and West elevations of the 2-story building. The overall placement of the roofing system is 90% complete which is ahead of schedule. Exterior windows are being installed along the East and West elevations of the 2-story building.
Schedule
|
Completion of Phase 1 |
December 31, 2008 |
| Completion of A/B Addition |
December 31, 2008 |
| Transition of Data System |
Complete |
| Commence Phase 2Work |
January 2009 |
| Commence Phase 3 Work |
June 2009 |
| Commence 4 Work |
August 2009 |
| Commence Phase 5 Work |
February 2010 |
| Completion of the Project |
August 1, 2010 |
 Placement of Exerior Insulation & Finish Systems (EIFS)
 Unit E Exterior Finish and Placement of New Roofing System
 Construction of Unit F Entrance and Cafeteria Expansion
 Installation of Drywall at Unit A Addition
 Erection of Mechanical/Electrical Lines at Cafeteria Expansion
 Units B & D, 2nd Floor, Installation of Overhead Finishes
 Units B & D, 2nd Floor, Classroom Finishes
 Placement of Foundations at Unit J Elevation/Stairs Addition
Click here for printable version.
Jeffersonville High School Project Overview
Units A/B - Addition Erection of structural steel and erection of exterior masonry are nearing completion. Placement of floor slabs is complete. Erection of metal stud framing along the East elevation of the existing building will be complete by Tuesday, August 6th thus allowing the placement of the roofing system.
Unit A – Future Science Classrooms All underground rough-ins are complete and the placement of the floor slabs is scheduled for Thursday, August 8th.
Units B and D, 2nd Floor Demolition is complete. Erection of mechanical/electrical overhead rough-ins continued. Masonry patching, masonry in-fills and erection of new masonry walls are complete.
Unit C – Future Science Classrooms Renovation Erection of ceiling grid and placement of new light fixtures are progressing and will be operational for the start of school. Casework has been delivered and will be set prior to the start of school.
Unit D - Classroom Renovation Ceiling systems are being erected within the room.
Unit E - Future MDF Room The transition of the data system occurred last month as scheduled. The ceiling system and placement of the remaining VCT will occur this month.
Unit E – Main Entrance Structural steel has been erected and erection of parapet wall has commenced. New entrances to the Media Center have occurred. This entrance will be utilized by the students and staff for the start of school.
Unit F – Entrance Building foundations have been poured and placement of the floor slab is scheduled for Monday, August 5th. Steel erection will commence after the slab placement. This entrance will be utilized by the students and staff for the start of school.
Boiler Room The new electrical switchgear and exterior transformers were energized during the month of July. In addition, the gas company has routed their new gas line to the new gas meter. The mechanical contractor is scheduled to route his line from the meter to inside the building prior to the start of school.
Unit J – Gymnasium The new mechanical units have been set and erection of new mechanical ductwork is complete. New sprinkler piping has been erected outside the mechanical rooms.
Exterior Shell of the Building The EIFS system is currently being erected along the West elevation and they will proceed to the East elevation once they are complete with the West elevation. A new roofing system has been placed on 90% of the existing roof system.
Schedule
| Completion of Phase 1 |
December 31, 2008 |
| Completion of A/B Addition |
December 31, 2008 |
| Transition of Data System |
Complete |
| Commence Phase 2 Work |
January 2009 |
| Commence Phase 3 Work |
June 2009 |
| Commence Phase 4 Work |
August 2009 |
| Commence Phase 5 Work |
February 2010 |
| Completion of the Project |
August 1, 2010 |
 New main entrance
 Erection of new dictwork within main gymnasium
 Building foundations at cafeteria expansion
 New exterior skin along west elevation
 New entrance to unit E
 Installation of EIFS along west elevation
Click here for printable version.
Jeffersonville High School Project Overview
Units A/B - Addition Foundations are complete and facebrick is being erected on the exterior skin of the building. Mechanical and electrical underground continue to be placed within the building footprint. Placement of floor slabs is scheduled for July 2nd and 7th. Erection of remaining structural steel will commence subsequent to the placement of slabs.
Unit A – Future Science Classrooms Demolition is complete and the General Contractor is proceeding on foundations.
Units B and D, 2nd Floor Demolition of carpeting is complete in the classrooms and the only areas that remain are the corridors. Overhead and wall rough-ins continue.
Unit C – Future Science Classrooms Renovation Underground installations are complete. Placement of slab is scheduled for July 7th.
Unit D - Classroom Renovation Masonry walls are being painted and overhead installations continue to be erected.
Unit E - Future MDF Room Interior walls have been painted and the placement of the flooring system is complete. MDF equipment will be set on July 3rd. This room is expected to be turned-over to the Owner during the 2nd week of July.
Unit E – Main Entrance Demolition and steel erection is complete. During the week of June 30th, the underground plumbing line will be installed.
Unit F – Entrance Building foundations have been determined and excavation of foundations is expected to commence the first week of July.
Unit F - Boiler Room Back-filling and the placement of underground plumbing is complete within the recessed area of the boiler room. Slab placement will be performed during the 2nd week of July.
Electrical switchgear is set and the electrical wire has been pulled from the switchgear to the exterior location of the new transformers. Duke Energy has approved this installation and will proceed on installing their feeders from the transformers to the street location.
Unit J – Gymnasium Demolition of the ductwork system is complete and erection of the new spiral ductwork has started. Erection of the sprinkler system is complete for this area with the exception of the mechanical rooms.
Exterior Shell of the Building The removal of the exterior facebrick and masonry block at the West elevation of the 2-story building is complete. Parapet wall is being constructed along this elevation. General contractor is proceeding with the removal of the exterior skin along the South elevation.
Roof Level Placement of the new roofing system is approximately 50% complete.
Site Work As of June 30th, the gas company started the installation of the new gas line from Allison Lane to the new location of the meter. The setting of new meter(s) and the removal of the old meters will be complete prior to the start of school in the Fall.
Schedule
| Completion of Phase 1 |
December 31, 2008 |
| Completion of A/B Addition |
December 31, 2008 |
| Completion of Unit E, MDF Room |
July 3, 2008 |
| Commence Phase 2 Work |
January 2009 |
| Commence Phase 3 Work |
June 2009 |
| Commence Phase 4 Work |
August 2009 |
| Commence Phase 5 Work |
February 2010 |
| Completion of the Project |
August 1, 2010 |
Click here for printable version.
Jeffersonville High School Project Overview
Units A/B - Addition Placement of foundations is nearly complete. Majority of the structural steel is set with exception of the metal joists and decking. Exterior masonry walls are being erected. Mechanical and electrical underground continue to be placed within the building footprint in order to place the new concrete floors.
Unit J - Elevator/Stairs Addition Topsoil has been removed, demolition has been completed and a temporary fence has been erected in order to isolate this area from students. Placement of elevator foundations is being held-up due to an unforeseen storm line which is lying within our new building foundations.
Boiler Room One of the existing chillers has been relocated and reconnected at its temporary location. The old chiller and boilers have been removed from the building. We are in the process of back-filling the recess area of the boiler room in order to pour a new concrete slab at the same elevation as the surrounding slabs.
The new boilers and pumps have been set and pipe connection to the mechanical units is complete.
Unit A – Future Science Classrooms As of June 4th, we started demolition activities within this classroom which will be followed by new foundations.
Unit C – Future Science Classrooms Renovation Demolition activities and the placement of concrete are complete. We are currently working on erecting structural steel within this classroom.
Unit D - Classroom Renovation Demolition activities, erection of structural steel, placement of concrete and erection of masonry walls are complete. We are currently erecting new overhead installations within these classrooms.
Unit E - Future MDF Room Currently the Owner’s computer equipment has been relocated out of these rooms. The demolition activities and the erection of interior walls are complete. Painting is scheduled to start during the week of June 9th. Once the flooring and painting are complete, the new MDF equipment will be set and terminated.
Unit E – Main Entrance Started demolition activities at this building entrance and at the adjacent classroom.
Units B and D, 2nd Floor We have started the demolition activities for the 2nd floor classrooms.
Exterior Shell of the Building We have started the removal of exterior facebrick and masonry block at the West elevation of the 2-story building followed immediately with the installation of new metal studs and drywall.
Roof Level Existing chimney stack has been demolished to the roof level. Roofing contractor continues to vacuum/remove all the loose rock from the various roof levels. Application of the roofing system has commenced at the West elevation of the building and will proceed to the East elevation.
Site Work The feeder conduit from the new electrical transformers to the new switchgear location has been installed. The placement of the new transformer pads is complete and installation of the feeder conduit to Allison Lane is complete. The new transformers that were furnished by Duke Energy have been set and will be energized once the electrical feeds have been installed from the interior switchgear to the new transformers.
 Erection of exterior walls and structural steel at Units A/B
 Removal of main entrance tunnel
 Erection of new skin along west elevation
 Demolition of Unit E entrance
 Erection of masonry at Unit C science classroom
 Demolition of HVAC at gymnasium
Click here for printable version.
Jeffersonville High School Project Overview
Units A/B - Addition Placement of foundations is nearly complete and erection of structural steel is scheduled to commence during the week of May 12th. The mason continues to place foundation block. Backfilling of new foundations have started.
Unit J - Elevator/Stairs Addition Topsoil has been removed, demolition has been completed and a temporary fence has been erected in order to isolate this area from students. Excavation for elevator foundations will commence during the week of May 12th.
Boiler Room One of the existing chillers has been relocated and reconnected at its temporary location. The other chiller and boilers have been removed from the building. We are in the process of back-filling the recess area of the boiler room in order to pour a new concrete slab at the same elevation as the surrounding slabs.
The new boilers have been set and pipe connection to the units is complete. Boiler pumps are being delivered and set on their housekeeping pads.
Unit E - Future MDF Room (Main Distribution Frame) Currently the Owner’s computer equipment has been relocated out of these rooms. Erection of temporary partitions and demolition activities will be completed by the end of the month.
Unit D - Classroom Renovation Demolition within this classroom has been completed, structural steel has been erected and backfilling of the area is complete. Placement of concrete is scheduled for the week of May 12th.
Unit C - Science Classroom Renovation Demolition within this classroom is nearly complete. Saw-cutting and removal of existing slab for future foundations has started.
Roof Level Existing chimney stack has been demolished to the roof level. Roofing contractor is preparing to vacuum/remove all the loose rock from the roof level. Once this is complete, the roofing system will be installed from the West direction to the East portion of the building.
Site Work The feeder conduit from the new electrical transformers to the new switchgear location has been installed. The placement of the new transformer pads is complete and installation of the feeder conduit to Allison Lane is complete. We are now waiting on Duke Energy to set their new transformers and set a new utility pole along Allison Lane.