Jeffersonville High School Project Overview
Areas that have been renovated and turned-back over to the Owner:
-Replacement of the Exterior Skin of the Building along the North & South elevations.
-Removal of the old ductwork system and replacement with new installations on the 1st floor corridors.
-Main stairs have been removed and the new stairs have been erected. Majority of the finishes are complete with exception of the handrails.
-Old Administration Area has been converted into a new Clinic Area and Guidance Offices.
-Two existing science classrooms have been renovated.
- Units A and D, 2nd Floor, North and South Classrooms have been completed.
-Kitchen and Cafeteria Areas have been completely renovated.
-New Media Center is complete.
-Structural steel has been erected at the North and South entrances and final building finishes have been erected.
-Placement of the new Dumpster Area outside the Kitchen Area is complete.
-Painting of new installations within the Main and Auxiliary Gyms is complete.
Work continues at the following Areas:
-Renovation of 1st Floor, Science Classrooms and old Guidance Offices that were located along the South and West elevations of the 2-Story portion of the building.
-Renovation of 1st Floor classrooms that are located along the North and West elevations.
-Completion of (4) restrooms (1st & 2nd floors) next to the main stairs.
-Renovation of Boys PE Locker Rooms continues.
-Elevator and Stairs Addition continues.
-Unit K, Locker Room Addition continues.
-Unit G, Industrial Technology Area, pulling electrical wire from the switchgear to various electrical panels.
Schedule
|
Phase 1
|
Complete
|
|
A/B Addition
|
Complete
|
|
Transition of Data System
|
Complete
|
| Phase 2, 2nd Floor |
Complete
|
|
Phase 3, 2nd Floor
|
Complete
|
|
Phase 3A, 2nd Floor
|
Complete
|
|
Replace North & South Elevations of 2nd Story
|
Complete
|
|
Renovation of the Media Center
|
Complete
|
|
Renovation of the Kitchen & Cafeteria Areas
|
Complete
|
|
Commence Phase 4 Work
|
Started
|
|
Commence Phase 5 Work
|
Started
|
|
Replacement of the Main Stairs
|
Started
|
|
Completion of the Project
|
August 1, 2010 |