Jeffersonville High School Project Overview
The overall project is 61% complete.
Unit A - Old Administration Area and Science Classroom
During the 1st week of March we started demolition work within the old administration area. In addition, we recommenced our work within Unit A science classroom.
Unit B – New Addition, Science Rooms
Science classrooms have been turned-over to the Owner for occupancy.
Units B and D, 2nd Floor, Middle Section of Building
The next set of (16) classrooms are scheduled to be turned-over March 13th.
Unit F – Loading Dock Area
The new emergency generator was energized this past month. Continuing to route chilled water lines to the cooling towers and chillers.
Unit G – Industrial Art Classrooms (106, 107 & 108)
Demolition and placement of foundations within these classrooms is complete and we are ready for steel erection.
Units J / K – Locker Room / Mechanical Addition
Continuing to erect exterior masonry walls. Placement of floor slabs and setting of mechanical equipment are scheduled to be complete this month.
Schedule
| Completion of Phase I |
Complete |
| Completion of A/B Addition |
Complete |
| Transition of Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Replace North & South Elevations of the 2-Story |
August 2009 |
| Renovation of the Media Center |
August 2009 |
| Renovation of the Kitchen & Cafeteria Areas |
August 2009 |
| Replacement of the Main Stairs |
August 2009 |
| Completion Date for Phase 3, 2nd Floor |
March 2009 |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Commence Phase 4 Work |
April 2009 |
| Commence Phase 5 Work |
June 2009 |
| Completion of Project |
August 1, 2010 |
New Science Rooms
New Science Rooms

Renovation of 2nd Set of Classrooms
New Locker Rooms/Mechanical Mezzanine Addition
Click here for a printable version of this report.