Jeffersonville High School Project Overview
The overall project is 60% complete and we have expended approximately $22 million dollars.
Unit B - New Addition, Science Rooms
Casework has been installed. Mechanical and electrical hook-ups at each work station are complete.
Units B and D, 2nd Floor, Middle Section of Building
Interior finishes are proceeding and the turnover date for this phase is early March.
Unit F - Loading Dock Area
New Cooling Towers and Emergency Generator have been set in their permanent location outside the Boiler Room. We are proceeding on infilling existing louver openings and the setting of new louvers.
Unit F - Entrance and Cafeteria Expansion
Placement of exterior Patio Area and sidewalks/steps are complete.
Units J / K - Locker Room / Mechanical Addition
Structural Steel has been erected and detailed. Continuing to erect exterior masonry walls (weather dependant).
Schedule
| Completion of Phase I |
Complete |
| Completion of A/B Addition |
Complete |
| Transition Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
March 2009 |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Commence Phase 4 Work |
April 2009 |
| Commence Phase 5 Work |
June 2009 |
| Completion of the Project |
August 1, 2010 |
Setting of New Cooling Towers & Generator

Erection of Structural Steel @ Vestibule / Mechanical Room Addition

Placement of Cafeteria Patio and Steps

New Addition - Science Room

Renovation of 2nd Floor Classroom