Jeffersonville High School Project Overview

The overall project is 60% complete and we have expended approximately $22 million dollars.

Unit B - New Addition, Science Rooms
Casework has been installed. Mechanical and electrical hook-ups at each work station are complete.

Units B and D, 2nd Floor, Middle Section of Building
 Interior finishes are proceeding and the turnover date for this phase is early March.

Unit F - Loading Dock Area
New Cooling Towers and Emergency Generator have been set in their permanent location outside the Boiler Room. We are proceeding on infilling existing louver openings and the setting of new louvers.

Unit F - Entrance and Cafeteria Expansion
Placement of exterior Patio Area and sidewalks/steps are complete.

Units J / K - Locker Room / Mechanical Addition
Structural Steel has been erected and detailed. Continuing to erect exterior masonry walls (weather dependant).

Schedule

Completion of Phase I Complete
Completion of A/B Addition Complete
Transition Data System Complete
Completion Date for Phase 2, 2nd Floor Complete
Completion Date for Phase 3, 2nd Floor March 2009
Completion Date for Phase 3A, 2nd Floor June 2009
Commence Phase 4 Work April 2009
Commence Phase 5 Work June 2009
Completion of the Project August 1, 2010
















Setting of New Cooling Towers & Generator


Erection of Structural Steel @ Vestibule / Mechanical Room Addition


Placement of Cafeteria Patio and Steps


New Addition - Science Room


Renovation of 2nd Floor Classroom

Click here for printable version.

Link
Link
Email this
Email
Close
Send this Post
Your Name:


Your Email Address:


Recipient's Email Address:


Your Message:



7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS