Jeffersonville High School Project Overview

Units A/B - Addition
Erection of structural steel and erection of exterior masonry are nearing completion.  Placement of floor slabs is complete.  Erection of metal stud framing along the East elevation of the existing building will be complete by Tuesday, August 6th thus allowing the placement of the roofing system.

Unit A – Future Science Classrooms
All underground rough-ins are complete and the placement of the floor slabs is scheduled for Thursday, August 8th.

Units B and D, 2nd Floor
Demolition is complete.  Erection of mechanical/electrical overhead rough-ins continued.  Masonry patching, masonry in-fills and erection of new masonry walls are complete.

Unit C – Future Science Classrooms Renovation
Erection of ceiling grid and placement of new light fixtures are progressing and will be operational for the start of school.  Casework has been delivered and will be set prior to the start of school.

Unit D - Classroom Renovation
Ceiling systems are being erected within the room.

Unit E - Future MDF Room
The transition of the data system occurred last month as scheduled.  The ceiling system and placement of the remaining VCT will occur this month.

Unit E – Main Entrance
Structural steel has been erected and erection of parapet wall has commenced.  New entrances to the Media Center have occurred.  This entrance will be utilized by the students and staff for the start of school.

Unit F – Entrance
Building foundations have been poured and placement of the floor slab is scheduled for Monday, August 5th.  Steel erection will commence after the slab placement.  This entrance will be utilized by the students and staff for the start of school.

Boiler Room
The new electrical switchgear and exterior transformers were energized during the month of July.  In addition, the gas company has routed their new gas line to the new gas meter.  The mechanical contractor is scheduled to route his line from the meter to inside the building prior to the start of school.

Unit J – Gymnasium
The new mechanical units have been set and erection of new mechanical ductwork is complete.  New sprinkler piping has been erected outside the mechanical rooms.

Exterior Shell of the Building
The EIFS system is currently being erected along the West elevation and they will proceed to the East elevation once they are complete with the West elevation.  A new roofing system has been placed on 90% of the existing roof system. 

Schedule

Completion of Phase 1 December 31, 2008
Completion of A/B Addition December 31, 2008
Transition of Data System Complete
Commence Phase 2 Work January 2009
Commence Phase 3 Work June 2009
Commence Phase 4 Work August 2009
Commence Phase 5 Work February 2010
Completion of the Project August 1, 2010

Greater Clark blog
New main entrance

Greater Clark Construction blog
Erection of new dictwork within main gymnasium

Greater Clark blog
Building foundations at cafeteria expansion

Greater Clark Construction blog
New exterior skin along west elevation

Greater Clark Construction blog
New entrance to unit E

Greater Clark blog
Installation of EIFS along west elevation

Click here for printable version.

Link
Link
Email this
Email
Close
Send this Post
Your Name:


Your Email Address:


Recipient's Email Address:


Your Message:



7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS