Jeffersonville High School Project Overview
The overall project is 64% complete.
Unit A - Old Administration Area and Unit A - Science Classrooms
Continue to erect interior walls and install mechanical, electrical and plumbing rough-ins.
New masonry walls are complete.
Unit B – New Addition, Science Rooms
Demolition is complete and installation of underground plumbing lines has started.
Units B and D, 2nd Floor, North Section of Building
Demolition is complete and we have started installing mechanical and electrical overhead installations.
Unit F – Loading Dock Area
Cooling towers and (1) of the chillers are scheduled to be activated by May 1st.
Unit G – Industrial Art Classrooms (106, 107 & 108)
The elevated mechanical deck has been erected and the slab-on-deck has been placed. All mechanical / electrical equipment that rest on this deck are located on-site.
Units J / K – Locker Room / Mechanical Addition
A portion of the roofing system was placed during Spring Break.
The elevator contractor has mobilized and has started installation of the new elevator.
All new concrete slabs have been placed with the exception of the entrance to the Athletic Director’s office.
Schedule
| Completion of Phase 1 |
Complete |
| Completion of A/B Addition |
Complete |
| Transition of Data System |
Complete |
| Completion Date for Phase 2, 2nd Floor |
Complete |
| Completion Date for Phase 3, 2nd Floor |
Complete |
| Commence Phase 4 Work |
June 2009 |
| Commence Phase 5 Work |
Started |
| Completion Date for Phase 3A, 2nd Floor |
June 2009 |
| Replace North & South Elevations of the 2-Story |
August 2009 |
| Renovation of the Media Center |
August 2009 |
| Renovation of Kitchen & Cafeteria Areas |
August 2009 |
| Replacement of the Main Stars |
August 2009 |
| Completion of the Project |
August 1, 2010 |

Enclosure of Units F and J

Erection of new building skin along south elevation.
Erection of new walls at new administration area.
Interior Finishes at 2nd floor, middle corridor
Click here for printable version.