Floyd Central High School Project Overview
General Comments
None
Site Work
The installation of the storm line, curb, and sidewalk from Edwardsville-Galena Road up to the existing Football Field is completed. Seeding and straw have been completed outside the fence. We will begin demolition on the existing Football Field and start constructing the Parking Lot after the last Football Game.
New 2-story Classroom Addition
All structural steel has been set and steel detailing is nearly completed. Mechanical, electrical, plumbing, and fire protection rough-ins are continuing along with the framing. We will begin foam roofing, continue the brick work, and the elevator has been delivered.
New Art Rooms Addition
The punch list has been issued and is being completed. The new furniture has been delivered and installed. The certificate of occupancy was issued and the Owner has occupied the Art Rooms since the beginning of October.
North End of the Upper Level in the Auxiliary Gymnasium
Painting has been completed in the Wrestling, Dance, and Cardio Rooms. All of the new lights have been installed. The temporary walls have been removed and the new doors have been installed. Stair #17 has been set and the steps will be poured very soon. The elevator has been delivered and the installation has started. Ceramic tile in Restrooms C147 & C148 has been completed. Plumbing fixtures have been set and installation of the toilet partitions and accessories will begin.
New Band/Orchestra Addition
Several of the masonry walls were damaged in the wind storm and have been cleaned up and rebuilt. Masonry is currently 60% complete. Structural Steel components are being set. The 2nd floor slabs have started to be poured. The schedule is approximately 4 weeks behind, due to the wind storm on September 14, 2008.
ROTC/Cross Cut Hallway/Gym Locker Rooms
ROTC: Painting, acoustical ceilings, ceramic tile, plumbing fixtures, and lockers are completed. Flooring has started and doors & hardware will be done as the flooring is completed. Stair #20 to the Commons Area is being set and poured. The Owner move in is schedule for this week.
Cross Cut Hallway: Painting and wood trim is completed. Acoustical ceiling is nearly completed. Floor will be leveled and installation of flooring will begin. The Owner will move-in prior to the flooring being completed. The Owner move-in is scheduled for this week.
Gym Locker Rooms: The lockers and acoustical ceilings are completed. The ceramic tile has started and installation of plumbing fixtures, toilet partitions, toilet accessories, and doors and hardware will begin. The Owner move-in is scheduled for this week.
Pool/Pool Storage Rooms
Pool: Demolition of the old pool equipment has completed. We have started installing the new pool equipment and will continue with mechanical, electrical, plumbing and fire rough-ins. We will start painting the Pool Room and begin patching and coating the Pool.
Pool Storage Rooms: We will begin final painting this week.
Commons Area Steel/Commons Restrooms
Commons Area Steel: The installations of the metal panels and windows have started. We will continue with the foam roofing.
Commons Restroom: The restrooms have been completed and are open for use.
Mechanical Pipe Routes
The mechanical room work will continue throughout the project.
Existing Art Rooms (Industrial Tech):
The temporary wall has been constructed and demolition is nearly completed. The framing and rough-ins have started. We will begin replacing the exterior brick and a temporary fence has been installed to separate students from workers at this location.

Art Room

Started demolition in the Existing Art Rooms