Floyd Central High School Project Overview

General Comments
None

Site Work
The site demolition at the new 2-story addition for the Band/Orchestra area is nearly complete except for entrance.

The relocation of the storm utilities at the rear of the school is nearly complete.  Site demolition for partial Tennis Courts behind Galena, will complete demolition and install parking lot this summer.

New 2-story Classroom Addition
All footings and foundations are nearly complete; masonry bearing walls have been started.  Structural steel is being delivered and erection has begun.  Underground plumbing is nearly completed.  The slab on grade work will start in the near future. 

New Art Rooms Addition
The installation of underground plumbing and electrical is complete.  The foundations are also complete.  The structural steel erection is nearly complete.  MEP/FP Rough-ins have started.  Metal stud framing on Roof has started.  The slab on grade work has started this week.

North End of the Upper Level in the Auxiliary Gymnasium
The walls have been erected along with the new door and window frames.  The mechanical, electrical, and fire protection rough-ins are continuing.  Drywall is currently being installed.  Demolition is continuing at the racquetball courts.  These areas will become the new wrestling room, weight lifting room, cardio room, and dance room.  The East elevator and the SW Stair demolition are nearly completed.

Main Gym Locker Rooms / Basement (Existing ROTC location) / New Hallway
Main Gym Locker Room – Demolition is complete.  Mechanical, electrical, plumbing, and fire rough-ins are continuing.  Masonry walls are continuing.

ROTC – Demolition and metal stud framing are complete, drywall is nearly complete.  MEP/FP rough-ins are continuing.

Storage Rooms in Pool Area
The pool has been drained.  The new construction of the Temporary Classrooms in the pool has started.  Mechanical, electrical, plumbing, and fire rough-ins have started.  Demolition of new door openings has been completed in the Storage Room’s from Hallway.

Construction Dates:

New 2-story Classroom Addition     January 14, 2008 to March 20, 2009
New Art Rooms Addition     March 3, 2008 to August 1, 2008
Main Gym Locker Rooms/Basement (Existing ROTC location)/New Hallway March 4, 2008 to October 10, 2008
Storage Rooms in Pool Area     April 28, 2008 to October 6, 2008
Mechanical/Electrical/Ductwork Routing    February 18, 2008 to January 1, 2009

 Click here for printable version.

 

Link
Link
Email this
Email
Close
Send this Post
Your Name:


Your Email Address:


Recipient's Email Address:


Your Message:



7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS