Floyd Central High School Project Overview
General Comments
None
Site Work
The site demolition of the parking lots and drives is nearly complete. The Site Utilities are being relocated and new storm lines are being installed. Site fence at the new 2-story addition has been removed and re-installed to make room for the new curbs and asphalt base to be installed this summer.
Site demolition of the Tennis Courts behind Galena is complete and the installation of the storm utilities is continuing. The curbs, sidewalks, and asphalt base will follow this summer.
New 2-story Classroom Addition
The masonry bearing walls will start in the near future. Structural steel erection is continuing. Underground plumbing is complete.
New Art Rooms Addition
The colored concrete slab has been poured. Metal stud framing has begun. Foamed roof is to be installed this week. MEP/FP rough-ins are continuing.
North Half of Commons Area
The roof demolition for the new columns is complete. Demo of restrooms by ROTC steps has begun. They will start setting new columns very soon.
North End of the Upper Level in the Auxiliary Gymnasium
The mechanical, electrical, and fire protection rough-ins are continuing. The East elevator and the Stair #17 demolition are nearly completed. Masonry is complete at the old racquetball courts. We will begin setting steel and will follow with 2nd floor concrete pour.
New Band/Orchestra Addition
The construction of the new building pad is nearly complete. The foundations and underground work will start immediately after the pad is completed.
Main Gym Locker Rooms / Basement (Existing ROTC location) / New Hallway
Main Gym Locker Room – Demolition is complete. Mechanical, electrical, plumbing, and fire rough-ins are continuing. Masonry walls are continuing.
ROTC – MEP/FP rough-ins are continuing.
Storage Rooms in Pool Area
Door frames have been set. Mechanical, Electrical, Plumbing, and Fire Protection rough-ins are continuing. Masonry work is also continuing.
Mechanical/Electrical Pipe Routes
Demolition of the old mechanical room is complete. The continuations of the new pipe routes to the additions are on-going. Demo for new electrical closet near Special Education room has started. The electrical power shutdown work to install new transformer should be complete this week.
| New 2-story Classroom Addition |
January 14, 2008 to March 20, 2009 |
| New Art Rooms Addition |
March 3, 2008 to August 7, 2008 |
| North Half Commons Area |
March 24, 2008 to August 1, 2008 |
| Upper Level of Aux. Gym |
February 18, 2008 to January 3, 2009 |
| Existing Art Rooms |
June 2, 2008 to September 22, 2008 |
| Main Gym Locker Rooms/Basement (Existing ROTC Location)/New Hallway |
March 4, 2008 to October 10, 2008 |
| Storage Rooms in Pool Area |
April 28, 2008 to October 6, 2008 |
| Mechanical/Electrical/Ductwork Routing |
February 18, 2008 to January 2, 2009 |