Floyd Central High School Project Overview
Site Work
The site work at the new Band Storage Area is complete. Partial Punch List has been issued and will be completed in spring/early summer. There is a small amount of site work at the lay down area which is scheduled to be completed early summer.
New 2-story Classroom Addition – Administration Area
The terrazzo design and colors are being selected. The terrazzo at the Main Rotunda is scheduled to be completed in June.
Partial Upper Unit C / Unit A (Band / Orchestra Addition)
Will continue working on the flooring, casework and display cabinets in front of the Auditorium.
Pool/Pool Storage Rooms
The Pool is complete, including the HVAC unit.
Commons Area
The ceramic tile is 60% complete. Will continue working on the flooring. The display cabinets are ready to be installed.
Mechanical Pipe Routes
The mechanical room work will continue throughout the project.
New Kitchen & Cafeteria
Will continue working on installing the casework (barstool tops) in the cafeteria.
New Science Rooms
The Owner moved into these rooms prior to Christmas Break. Casework modifications will continue on second shift.
New Media Center
The Owner moved into this area in November. Work will continue on the display cabinets and on the punch list.
Unit B – Auditorium
The refinishing of the Stage flooring will be scheduled for a later time. Renovation of the old Black Box Theater has begun.
Skylights and Light Monitors
Several light monitors are complete. Will continue working on the rest of them, including the skylights, throughout the school year.
Partial Phase 3A
The demolition is complete on 30% of this phase. Framing is nearly complete for this portion. Underground plumbing and electric have begun and will continue. Drywall has been hung on Corridor walls and some new lockers have been installed. This phase is scheduled to be complete the beginning of March; then will begin work on the remaining portion.
Old Media Center
The demolition and framing are complete, drywall hanging and finishing is 60% complete. Ceilings, casework, and flooring will begin. The CAD Room drywall is nearly completed. These areas are scheduled to be completed February 28th. The Owner has moved into one room already.
Click here for a printable version of this report.