Floyd Central High School Project Overview
Site Work
We will begin removal of the lay down area during the month of May and should be complete by the end of May. Contractors have started removing items no longer needed and some of the empty storage units have been removed. Will complete the remaining light poles and finish the site work. The remaining Progress Meetings after May 25th will be held in the Distant Learning Room until completion of the project.
New 2-story Classroom Addition – Administration Area
The terrazzo in the Rotunda is complete.
Partial Upper Unit C / Unit A (Band / Orchestra Addition)
The painting of the Upper East Side of the Gym has been completed; the rest of the Gym will be painted and the Gym floor will be refinished during the summer break. Installation of the new baseball nets, divider curtains and relocation of the basketball goals has begun.
Commons Area
The ceramic tile is being completed outside the Cafeteria; the punch list has been issued and should be completed prior to Graduation.
Mechanical Pipe Routes
The pipe routes are complete throughout the building with the exception of some old piping in the hallway by the Two Story Addition that needs to be demo’d during the summer break.
New Kitchen & Cafeteria
The bar stool tops have been installed in the Cafeteria.
New Science Rooms
The casework modifications have been completed and the punch list is being issued. The additional work for the gas shut off valves has been approved and the work will be completed during the summer break.
New Media Center
The display cabinets have been completed.
Unit B – Auditorium
The refinishing of the Stage flooring and painting will be done during the summer break. The renovation of the old Black Box Theater has been completed.
Skylights and Light Monitors
All of the light monitors are complete and the skylights will be installed during the summer break.
Partial Phase 3A
The framing and masonry are complete. The drywall is 75% complete. The ceiling grid and painting have begun and the last of the student restrooms are 30% complete.
Old Media Center
This area is 100% complete, with the exception of the corridors. (Please refer to Corridors section below).
Main Gym
The painting and the motorized basketball goals are complete. The refinishing of the Gym floor will be completed over the summer break.
Corridors
The School’s “A” Hallway and partial “B” Hallway, skylights, ceilings, bulkhead and the flooring will be completed during the summer break. The remaining lockers are scheduled to be installed May 22nd. All other corridors will be complete with the exception of some flooring where the temporary lockers are in use, the flooring in these areas will be completed during the summer break.
New Tile Flooring in Commons Area at Entrance to Cafeteria
New Distance Learning Room
Rotunda Terrazzo Logo

Student Restrooms in Phase 3A