Floyd Central High School Project Overview

General Comments
None

Site Work
Installing storm lines at new parking area; completed demo; begin installation of base course; install parking lot lights; complete new entrance from Old Vincennes; install curbs and walks at Southwest corner by new ITE Labs; install walks at Band Addition for egress to student parking lot.

New 2-story Classroom Addition
Foam roofing is nearly complete; brick veneer continues; begin installation of windows behind brickwork; continue with temporary enclosures; begin drywall and finishes as areas are enclosed; mechanical, electrical, plumbing and fire rough-ins are continuing; will start elevator installation.

New Art Rooms Addition
We will move the CAD Teacher to the middle Art Room and work on completing Punch List items.

Partial Upper Unit C/Unit A
Unit C: Owner will move in upstairs Gym except for Weight Room. Need to complete masonry in Weight Room and paint. Lights in elevator are complete and restrooms in front of auditorium are complete.

Unit A: Brick veneer on North and South sides are complete, all second floor concrete is complete, masonry is nearly complete, tunnel entrance will be blocked off and egress moved to the North and South until Rotunda Area is complete.

ROTC/Cross Cut Hallway/Gym Locker Rooms
ROTC: Owner has moved in and Punch List has been issued.

Cross Cut Hallway: Complete except for flooring and Punch List being issued.

Gym Locker Rooms: Owner has moved in.

Pool/Pool Storage Rooms
Pool: Demolition of pool equipment is complete. Began installation of new pool equipment and will continue with mechanical, electrical, plumbing, fire rough-ins. Will start painting Pool Room and begin patching and coating the pool.

Pool Storage Rooms: The floor is installed. Will begin painting, installation of doors and hardware, and installation of temporary doors to pool and open pool hallway.

Commons Area Steel:
Commons Area Steel: Metal panels and windows are nearly complete. Will continue with relocation of utilities. Lower roof to be removed in the Summer of 2009.

Mechanical Pipe Routes
The mechanical room work will continue throughout the project.

Existing Art Rooms (Industrial Tech):
Demolition complete, framing complete, masonry complete, drywall and insulation complete, drywall finishes nearly complete, mechanical, electrical, plumbing, and fire rough-ins nearly complete, painting and acoustical panels will begin.


New ROTC Area


New Main Entrance


Old Football Field


Steel at the Band/Orchestra Addition


New Crosscut Corrider


Classroom Two-Story Addition at the Rotunda

Click here for printable version.

Link
Link
Email this
Email
Close

7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS