Site Work

 

All sidewalks, seeding and paving have been completed with the exception of the rear of the building.  Masonry on Storage Room (B170) and work on the exterior patio off of the Cafeteria have started.  The curbs, sidewalks and seeding at the rear of the building should be complete this week.  The installation of the exterior light poles has started and we will complete the installation of the flag pole this week.

 

 

New 2-story Classroom Addition – Administration Area

 

We have completed the resealing of the block within the corridors.  The Main Rotunda and doorways to the Office Area are complete with the exception of the terrazzo flooring, which will be completed next summer.

 

 

Partial Upper Unit C / Unit A (Band / Orchestra Addition)

 

Unit C:  All ceilings and Health Rooms are complete.  Training Room and Concession Stand is nearly complete.

 

Unit A:  Rotunda is complete including the flooring.  The display cabinets should be completed within the next month.

 

 

Pool/Pool Storage Rooms

 

Pool:  The pool liner is nearly complete and we will begin resinous flooring on August 17th.

 

Pool Storage Rooms:  These rooms are complete and have been turned over for the Owner’s use.

 

 

Commons Area Steel

 

All steel and glass are complete.  The finishes are 90% complete.  We will continue on the lighting and will start the work on the wood trim and display cabinets.  We will schedule the acoustical clouds and flooring throughout the school year.

 

 

Mechanical Pipe Routes

 

The mechanical room work will continue throughout the project.

 

 

Aux Gym Locker Rooms

 

East locker rooms are complete and are turned over for the Owner’s use.

 

The Middle and West Locker Rooms masonry work and locker benches are complete.  The painting and ceiling grid work have started.  The lockers have been delivered and installation will begin soon.  The doors have been installed.

 

 

New Kitchen & Cafeteria

 

All work in the Kitchen, including the equipment, is complete and in working order.  The Cafeteria is complete with the exception of the new storefronts/doors leading to the Commons and hallways.  The ceiling at the rotunda within the cafeteria will be continuing.  The casework on the North wall that joins the Commons will be completed this week.

 

 

New Special Ed Area – FACS Lab

 

Area is complete and ready for Punch List.

 

 

Four Classrooms at West End

 

Area is complete and ready for Punch List.

 

 

New Science Rooms

 

Metal stud framing and drywall are complete, masonry is 30% complete and the mechanical, electrical, fire and plumbing rough-ins are about 50% complete.

 

 

New Media Center

 

Metal stud framing is 90% complete, drywall has been installed on the corridor walls, masonry has started and the mechanical, electrical, fire and plumbing rough-ins are continuing.

 

 

Unit B – Auditorium

 

New pit wall is nearly complete.  All flooring, seating, Dressing Rooms and Restrooms are complete.  The stage floor refinishing will be scheduled at a later time.


Click here for a printable version of this report.


Link
Link
Email this
Email
Close

7240 Georgetown Road, Indianapolis, IN 46268 / Phone: (317) 297-7054 / Fax: (317) 298-7045
© 2008 Verkler Incorporated | All Rights Reserved | Website Content Management by Marketpath CMS